Briefing/projectactive
Whiskey BESS is a 154 MW Battery project in Texas, currently active.
Whiskey BESS LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-07-31.
- Queue ID
- ERCOT-25INR0253
- Location
- Van Zandt, Texas
- Technology
- Battery
- Developer
- Whiskey BESS LLC
- Market / region
- ERCOT
- Point of interconnection
- 6828 Canton Tap 138 kV
What stands out
1
Whiskey BESS is a 154 MW Battery project in Texas with status active.
2
Whiskey BESS LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-07-31.
Market and operating context
- Queue date
- 2022-12-07
- Proposed COD
- 2027-07-31
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.