Apache Hill BESS (ERCOT-25INR0231) — Project Summary

Queue ID
ERCOT-25INR0231
Capacity
201.15 MW
Technology
Battery
Status
active
Location
Hood, TX
Region
ERCOT
Developer
APACHE HILL ENERGY CENTER
IA Status
IA Executed

Apache Hill BESS

ERCOT-25INR0231BetaActiveBatteryERCOTLBNL + Live

201.15 MW storage in Hood, TX · In queue since November 2022 · Proposed COD October 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

201.15 MW

Capacity

1

Components

Battery

4 years

In Queue

IA Executed

IA Phase

Signed Jun 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 7m

IA → COD

2y 4m

Total Duration

1y 7m

Schedule

1 months past proposed COD

Construction75%
Queue EntryNov 7, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJun 26, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-10-31

Queue history
25INR0231 · 48 monthly ERCOT reports, Oct 2022 – Sep 2026

Projected COD moved

5 times

Aug 2024 → Oct 2026

Net change

+26 months

first report to latest

Capacity

201 → 201 MW

changed in the reports

Latest stage

Energized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 7, 2022
Facilities study approvedMar 10, 2026
Interconnection agreement signedJun 26, 2024
Approved for energizationSep 18, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Nov 2026
Differs from queue: Oct 31, 2026From queue filing
Developer in saved assessment
Vitis Energy
Ownership change in saved research
Status at research time
Construction
Construction — project nearing completion as of May 2026 per MasTec contractor updates, on track for November 2026 COD
Financing
Secured
Financing secured through acquisition by Vitis Energy in August 2024; specific financing terms not publicly disclosed
Ownership history
  1. 2024-08·Black Mountain Energy Storage→Vitis Energyenergy-storage.news

Milestones in this assessment

IA executedJun 26, 2024

Interconnection Agreement executed with ERCOT

interconnection.fyi
Ownership changeAug 2024

Vitis Energy acquired 200MW project from Black Mountain Energy Storage

energy-storage.news
GroundbreakingJun 2025

Construction began on Apache Hill BESS in Hood County

facebook.com
COD targetNov 2026Latest in this assessment

Expected online November 2026 per LBNL queue and construction timeline

cleanview.co
Research sources and reasoning (6 recorded sources)

high confidence at research time

  1. energy-storage.news/developer-black-mountain-sells-200mw-ercot-bess-to-woman-owned-ipp-vitis/
  2. hcnews.com/stories/dont-bess-with-texas,81677
  3. hcnews.com/stories/bess-facility-prompts-concerns-for-county-leaders-residents,123164
  4. facebook.com/MasTecCEI/posts/as-the-apache-hill-project-winds-down-we-are-taking-a-moment-to-recognize-the-im/1645053687119487/
  5. linkedin.com/posts/mike-russell-398780158_masteccei-mastec-bess-activity-7421922265728126976-VUkP
  6. facebook.com/groups/erathcountystopsolarfarmshere/posts/1662195627823452/

Commercial operation date: LBNL proposed COD of November 2026 aligns with construction timeline evidenced by MasTec Facebook post from May 2026 stating 'as the Apache Hill project winds down' and multiple Hood County News articles from mid-2025 confirming construction had begun.

Developer: Energy-Storage.News reported on August 28, 2024 that 'IPP Vitis Energy has acquired a 200MW BESS project in the ERCOT, Texas market from developer Black Mountain Energy Storage (BMES).' APACHE HILL ENERGY CENTER is the LBNL filing entity, but operational ownership transferred to Vitis Energy.

Status: LBNL shows 'active' with IA executed June 2024. Multiple sources confirm construction began by mid-2025 (Hood County News, Facebook posts). MasTec post from May 2026 states project is 'winding down,' indicating late-stage construction.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Apache Hill BESS project is a proposed 200.92 MW battery storage project located in Hood County, Texas. It is being developed by Apache Hill Energy Center and is interconnected within the ERCOT region under queue ID ERCOT-25INR0231. The project entered the interconnection queue on November 7, 2022, with a proposed commercial operation date of July 31, 2026.

The project's Interconnection Agreement (IA) has been executed as of June 26, 2024. The Point of Interconnection (POI) is the 363 Hood 138kV substation.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Hood

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

APACHE HILL ENERGY CENTER

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

363 Hood 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
DC2SES_ALL

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.