Briefing/projectactive
Apache Hill BESS is a 201 MW Battery project in Texas, currently active.
Apache Hill Energy Center is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-11-01.
- Queue ID
- ERCOT-25INR0231
- Location
- Hood, Texas
- Technology
- Battery
- Developer
- Apache Hill Energy Center
- Market / region
- ERCOT
- Point of interconnection
- 363 Hood 138kV
What stands out
1
Apache Hill BESS is a 201 MW Battery project in Texas with status active.
2
Apache Hill Energy Center is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2026-11-01.
Market and operating context
- Queue date
- 2022-11-07
- Proposed COD
- 2026-11-01
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.