Middlebrook BESS
158.63 MW generation in Nacogdoches, TX · In queue since October 2022 · Proposed COD June 2027
158.63 MW
Capacity
1
Components
Battery
4y 1m
In Queue
IA Executed
IA Phase
Signed Jul 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 9m
IA → COD
1y 11m
Total Duration
2y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-06-30
Projected COD moved
3 times
May 2025 → Jun 2027
Net change
+25 months
first report to latest
Capacity
303 → 159 MW
changed in the reports
Latest stage
Cancelled
last listed Dec 2025
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Project withdrawn from ERCOT queue per inactive project tracking
facebook.comResearch sources and reasoning (5 recorded sources)
high confidence at research time
- interconnection.fyi/project/ercot-25inr0215
- facebook.com/groups/671721666647600/posts/2294189637734120/
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- ercot.com/files/docs/2026/01/08/Capacity-Changes-by-Fuel-Type-Charts_December_2025.xlsx
- facebook.com/groups/erathcountystopsolarfarmshere/posts/1581420775900938/
Commercial operation date: LBNL queue snapshot shows proposed COD of 2027-06-30. ERCOT capacity chart (Result 8) confirms 2027 target year. No contradictory news sources found.
Developer: LBNL filing entity is 'Middlebrook Solar LLC'. No press releases or corporate announcements found identifying a parent company. PUC filing (Result 5) confirms same entity name. Appears to be project-specific LLC with no public parent disclosed.
Status: LBNL shows 'active' with IA executed 2025-07-21, but multiple February 2026 sources (Results 4, 6, 9, 12) confirm project withdrawal. Interconnection.fyi (Result 6) explicitly states 'currently withdrawn'. Facebook posts tracking ERCOT cancellations list withdrawal date of 01/21/2026 or 02/03/2025.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Middlebrook BESS is a proposed 158.63 MW battery storage project located in Nacogdoches County, Texas. The project, developed by Middlebrook Solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0215, with a queue entry date of October 24, 2022. The proposed commercial operation date is June 30, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Tap Stryker [3109] - Lufkin [3117] 345 kV line.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Dec 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Nacogdoches
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Middlebrook Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3109 Stryker - 3117 Lufkin
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.