Middlebrook BESS is a 159 MW Solar+Battery project in Texas, currently active.
Middlebrook Solar LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-06-30.
- Queue ID
- ERCOT-25INR0215
- Location
- Nacogdoches, Texas
- Technology
- Solar+Battery
- Developer
- Middlebrook Solar LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345kV 3109 Stryker - 3117 Lufkin
What stands out
1
Middlebrook BESS is a 159 MW Solar+Battery project in Texas with status active.
2
Middlebrook Solar LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-06-30.
Market and operating context
- Queue date
- 2022-10-24
- Proposed COD
- 2027-06-30
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.