Bonham Solar SLF
138.4 MW hybrid in Limestone, TX · In queue since November 2022 · Proposed COD April 2027
138.4 MW
Capacity
1
Components
Solar
4 years
In Queue
IA Executed
IA Phase
Signed Aug 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 9m
IA → COD
2y 8m
Total Duration
1y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2027-04-06
Projected COD moved
3 times
Feb 2025 → Apr 2027
Net change
+26 months
first report to latest
Capacity
140 → 138 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Proposed commercial operation date per ERCOT grid study
ercot.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/developers/x-elio
- interconnection.fyi/project/ercot-25inr0199
- ercotqueue.com/project/25INR0199
- ercot.com/files/docs/2026/03/17/EIR_Oncor_Southern_DFW_Load_Interconnection_Project_StatusUpdate_RPG_Mar_2026.pdf
- ercot.com/files/docs/2025/12/16/EIR_Status_Update_Oncor_Skyview_345138kV_Switch_Project_-_RPG_Dec_2025.pdf
Commercial operation date: LBNL queue snapshot shows proposed COD of April 6, 2027. Multiple ERCOT documents (December 2025 and March 2026 grid studies) confirm this same date. No contradictory news or press releases found.
Developer: LBNL filing entity is 'J&J Solar Ranch LLC' (project shell). Cleanview's X-Elio developer page lists Bonham Solar SLF as a 138 MW project in their pipeline, indicating X-Elio is the operating parent company behind the J&J Solar Ranch LLC filing entity.
Status: LBNL shows 'active' status with IA executed on August 7, 2024. ERCOTqueue.com confirms 'IA, FIS pending' status as of May 2026. ERCOT grid study documents from December 2025 and March 2026 include the project in active interconnection planning.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The XE Bonham Solar 1 project is a proposed solar generation facility with a total capacity of 138.4 MW. It is located in Limestone County, Texas, within the ERCOT region. The developer is J&J Solar Ranch LLC.
The project is listed in the ERCOT interconnection queue as entry ERCOT-25INR0199, with a queue entry date of November 15, 2022, and a proposed commercial operation date of April 6, 2027. The project's Interconnection Agreement (IA) has been executed as of August 7, 2024.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Limestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
J&J Solar Ranch LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 138 kV MEXIA_2_1_8 3632 - GROES_SE1_8 3634
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.