Briefing/projectactive
Bonham Solar SLF is a 138 MW Solar+Battery project in Texas, currently active.
J&J Solar Ranch LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-04-06.
- Queue ID
- ERCOT-25INR0199
- Location
- Limestone, Texas
- Technology
- Solar+Battery
- Developer
- J&J Solar Ranch LLC
- Market / region
- ERCOT
- Point of interconnection
- TAP 138 kV MEXIA_2_1_8 3632 - GROES_SE1_8 3634
What stands out
1
Bonham Solar SLF is a 138 MW Solar+Battery project in Texas with status active.
2
J&J Solar Ranch LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-04-06.
Market and operating context
- Queue date
- 2022-11-15
- Proposed COD
- 2027-04-06
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.