Staccato BESS
201.8 MW storage in Fayette, TX · In queue since November 2022 · Proposed COD May 2027
201.8 MW
Capacity
1
Components
Battery
4 years
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-28
Projected COD moved
4 times
Jul 2025 → May 2027
Net change
+22 months
first report to latest
Capacity
203 → 202 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
County approval granted; Commissioner McBroom involvement noted in August 2024 coverage
fayettecountyrecord.comNeighbor lawsuit dismissed by visiting judge in April 2025
fayettecountyrecord.comResearch sources and reasoning (6 recorded sources)
medium confidence at research time
- fayettecountyrecord.com/news/battery-storage-lawsuit-dismissed
- fayettecountyrecord.com/news/closer-look-battery-storage-facility-project
- fayettecountyrecord.com/news/neighbors-against-battery-storage-site-appeal-lawsuit
- fayettecountyrecord.com/news/warda-battery-storage-saga-still-playing-out-court
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0189/staccato-bess
- swg.usace.army.mil/Portals/26/docs/regulatory/JDs/SWG-2024-00311_241217_NPR_AJD.pdf
Commercial operation date: LBNL queue shows 2026-12-31 COD. No press releases or developer announcements found with updated timeline; only local news coverage of permitting disputes. Cleanview aggregators echo the LBNL date.
Developer: LBNL filing entity 'Staccato Storage, LLC' matches news coverage exactly. No parent company or operating entity identified in any source; appears to be a project-specific LLC with no disclosed backing.
Status: LBNL shows 'active' in Facility Study phase. Local news confirms project not withdrawn despite neighbor lawsuits (dismissed April 2025, appeal filed May 2025). No construction or financing announcements found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Staccato BESS project is a proposed 202.65 MW battery storage project in Fayette County, Texas. Developed by Staccato Storage, LLC, the project consists of 202.65 MW of battery capacity. It is listed in the ERCOT interconnection queue as entry ERCOT-25INR0189, with a queue entry date of November 7, 2022.
The proposed commercial operation date for the Staccato BESS project is December 31, 2026. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the 138kV WARDA #7312.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Fayette
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Staccato Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138kV WARDA #7312.
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26