Legato BESS
202.65 MW storage in Wise, TX · In queue since September 2022 · Proposed COD April 2028
202.65 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-24
Projected COD moved
1 time
Jul 2025 → Apr 2028
Net change
+33 months
first report to latest
Capacity
203 MW
unchanged in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
No IA executed; project remains at Facility Study stage with 5% estimated build probability
ercotqueue.comResearch sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0184/legato-bess
- renewablesinfo.org/project/ercot-25inr0184-legato-bess
- interconnection.fyi/project/ercot-25inr0184
- ercotqueue.com/project/25INR0184
Commercial operation date: LBNL queue filing shows proposed COD of April 24, 2028. No independent news sources or press releases found to validate or contradict this date; all search results merely echo the LBNL queue data.
Developer: All sources consistently identify 'Legato Storage, LLC' as the developer. No parent company, operating entity, or ownership structure information found in search results. One result (Cleanview) associates the project with Samsung Renewable Energy's pipeline, but this appears to be a data aggregation artifact rather than confirmed ownership.
Status: LBNL status is 'active' at Facility Study stage with no IA date. All search results confirm active queue status with no evidence of construction activity, financing, or permitting milestones.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Legato BESS project is a proposed 202.65 MW battery storage project located in Wise County, Texas. Developed by Legato Storage, LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-25INR0184, with a queue entry date of September 27, 2022, and a proposed commercial operation date of April 24, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 138kV #608 Crafton Substation - #620 Bowie Substation. The Legato BESS project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wise
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Legato Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138kV #608 Crafton Substation - #620 Bowie Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Substation 41
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.