Query
Legato BESS
Type
Entity Briefing
Entity
Legato BESS
State
TN
Technology
battery
Generated
2026-10-19T22:25:46.300Z

Briefing on Legato BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
203 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-04-24
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Legato BESS is a 203 MW Battery project in Texas, currently active.

Legato Storage, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-04-24.

Queue ID
ERCOT-25INR0184
Location
Wise, Texas
Technology
Battery
Developer
Legato Storage, LLC
Market / region
ERCOT
Point of interconnection
138kV #608 Crafton Substation - #620 Bowie Substation

What stands out

1

Legato BESS is a 203 MW Battery project in Texas with status active.

2

Legato Storage, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-04-24.

Market and operating context

Queue date
2022-09-27
Proposed COD
2028-04-24
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Legato BESS — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0184
LocationWise, Texas
TechnologyBattery
DeveloperLegato Storage, LLC
Market / regionERCOT
Point of interconnection138kV #608 Crafton Substation - #620 Bowie Substation
Queue date2022-09-27
Proposed COD2028-04-24