Rose Quartz BESS
101.41 MW storage in Dimmit, TX · In queue since September 2022 · Proposed COD December 2026
101.41 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Facility Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
Projected COD moved
1 time
Nov 2025 → Dec 2026
Net change
+13 months
first report to latest
Capacity
101 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Dimmit County Commissioners Court agenda item for Rose Quartz BESS - Samsung C&T Renewables, LLC
cms9files.revize.comResearch sources and reasoning (3 recorded sources)
medium confidence at research time
- cms9files.revize.com/dimmittx/Commissioners%20Court%20Agenda%2072825.pdf
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0133/rose-quartz-bess
- interconnection.fyi/project/ercot-25inr0133
Commercial operation date: LBNL queue snapshot shows proposed COD of December 1, 2026. No independent news sources or press releases found to validate or contradict this date; all search results merely echo the LBNL queue data.
Developer: LBNL filing entity is 'Rose Quartz BESS, LLC' (project shell). Dimmit County Commissioners Court agenda (July 28, 2025) explicitly names 'Rose Quartz BESS - Samsung C&T Renewables, LLC' as the operating entity behind the project.
Status: LBNL status is 'active' with IA status at 'Facility Study'. Dimmit County agenda from July 2025 shows Samsung C&T engaging with local government, confirming active development.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Rose Quartz BESS project is a proposed 101.41 MW battery storage project located in Dimmit County, Texas. The project, developed by Rose Quartz BESS, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0133, with a queue entry date of September 2, 2022.
The proposed commercial operation date for the Rose Quartz BESS project is December 1, 2026. The project's interconnection agreement status is currently in the Facility Study phase. Recent news coverage has discussed the development project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Dimmit
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rose Quartz BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 8283 Asherton - 8613 Bigwells
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MCLNSLR_RN
- POI Substation
- Asherton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.