August Draw Solar
250 MW generation in Reeves, TX · In queue since September 2022 · Proposed COD June 2028
250 MW
Capacity
1
Components
Solar
4y 2m
In Queue
IA Executed
IA Phase
Signed Sep 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3 years
IA → COD
2y 9m
Total Duration
3 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2028-06-27
Projected COD moved
3 times
Mar 2025 → Jun 2028
Net change
+39 months
first report to latest
Capacity
250 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
- —·DBR (entity name unclear)→August Draw Solar, LLCreevescounty.org
Milestones in this assessment
ERCOT Standard Generation Interconnection Agreement executed with AEP Texas, filed with Texas PUC October 2025
interchange.puc.texas.govResearch sources and reasoning (3 recorded sources)
low confidence at research time
- interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=2273
- reevescounty.org/Home/Components/News/News/535/134?curm=6&cury=2026&npage=2
- ercotqueue.com/project/25INR0112
Commercial operation date: Only LBNL queue data provides a COD target of June 2028. No news sources or press releases discuss project timeline or construction schedule.
Developer: LBNL filing entity is August Draw Solar Holdings, LLC. No news sources identify a parent company or operating entity. Reeves County tax abatement notice references 'August Draw Solar, LLC, formerly known as DBR' suggesting possible prior entity name but no current parent identified.
Status: LBNL shows 'active' status with IA executed 2025-09-12. Texas PUC filing confirms ERCOT Standard Generation Interconnection Agreement between AEP Texas and August Draw Solar Holdings filed October 2025, corroborating active interconnection process.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
August Draw Energy is a proposed 250 MW solar generation project located in Reeves County, Texas. Developed by DBR Solar, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-25INR0112. The project entered the interconnection queue on September 15, 2022, and has a proposed commercial operation date of June 27, 2028. Its interconnection status is currently in the Facility Study phase.
The August Draw Energy project has been mentioned in recent news coverage related to industry and development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
August Draw Solar Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 60207 Verhalen – 60808 Hoefs Road
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesSolar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
August Draw Solar
Data-driven briefing on August Draw Solar — fleet, generation, financial, and news signals.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.