Diver Solar (ERCOT-25INR0105) — Project Summary

Queue ID
ERCOT-25INR0105
Capacity
225.59 MW
Technology
Solar
Status
active
Location
Limestone, TX
Region
ERCOT
Developer
Diver Solar
IA Status
IA Executed

Diver Solar

ERCOT-25INR0105BetaActiveSolarERCOTLBNL

225.59 MW generation in Limestone, TX · In queue since September 2022 · Proposed COD January 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

225.59 MW

Capacity

1

Components

Solar

4y 2m

In Queue

IA Executed

IA Phase

Signed Oct 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 1m

IA → COD

2y 3m

Total Duration

1y 1m

Schedule

11 months past proposed COD

Construction75%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 27, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-01-16

Queue history
25INR0105 · 42 monthly ERCOT reports, Aug 2022 – Jan 2026

Projected COD moved

4 times

Dec 2025 → Jan 2026

Net change

+1 months

first report to latest

Capacity

253 → 226 MW

changed in the reports

Latest stage

Commercial operation

last listed Jan 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 2, 2022
Facilities study approvedNov 9, 2024
Interconnection agreement signedOct 27, 2023
Approved for energizationJul 24, 2025
Approved for synchronizationAug 1, 2025
Approved for commercial operationFeb 2, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 18 months ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneconstruction started · 2025-05-01Construction Dive · 2025-05-13
Expected CODQ1 2026Construction Dive · 2025-05-13

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Aug 2025
Differs from queue: Jan 16, 2026
Developer in saved assessment
Diver Solar
Filed as Diver Solar, LLC
Status at research time
Online
Online — project became operational in August 2025, approximately 5 months ahead of LBNL's proposed COD
Financing
Secured
Financing secured (project completed construction and is operational); specific financing terms not publicly disclosed

Milestones in this assessment

IA executedOct 27, 2023

Interconnection Agreement executed with ERCOT

cleanview.co
COD targetAug 2025Latest in this assessment

Project built and became operational in August 2025

cleanview.co
Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. cleanview.co/solar-farms/texas/68483/diver-solar-llc
  2. interconnection.fyi/project/ercot-25inr0105
  3. gem.wiki/Diver_solar_farm
  4. assets.comptroller.texas.gov/ch313/1900/1900-grosebeckisd-stetson-amendapp1.pdf

Commercial operation date: LBNL proposed COD was 2026-01-16, but Cleanview reports the project was built in August 2025, and both interconnection.fyi and Global Energy Monitor confirm the project is now operational. The project came online ~5 months earlier than the LBNL queue date.

Developer: LBNL filing entity is 'Diver Solar, LLC' (confirmed in Texas Comptroller Ch. 313 tax abatement documents). No parent company or operating entity distinct from the project LLC was identified in available sources, suggesting this may be a single-purpose project vehicle.

Status: Multiple independent sources (Cleanview, interconnection.fyi, Global Energy Monitor) confirm operational status as of late 2025/early 2026, superseding LBNL's 'Active' queue status.

Project lifecycle
as of 2025-05-13
PhaseConstructionConstruction Dive · 2025-05-13
OperationalNoConstruction Dive · 2025-05-13
TechnologySolarConstruction Dive · 2025-05-13
DeveloperArevon EnergyConstruction Dive · 2025-05-13
PPA offtakerMetaConstruction Dive · 2025-05-13
EPC contractorPrimoris Services Corp.Construction Dive · 2025-05-13
GroundbreakingAnnouncedConstruction Dive · 2025-05-13

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Diver Solar SLF is a proposed 225.59 MW solar generation project located in Limestone County, Texas. The developer is Diver Solar. The project is interconnected within the ERCOT region under queue ID ERCOT-25INR0105, with an interconnection queue entry date of September 2, 2022, and a proposed commercial operation date of June 30, 2026. The project's Interconnection Agreement (IA) was executed on October 27, 2023.

The proposed project is linked to the existing Diver Solar, LLC operating plant (EIA plant ID 68483). Recent news coverage has discussed the project in the context of industry and grid developments.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Jan 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Limestone

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Diver Solar

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 3384 St Johns - 3390 Jewett

Data Source

LBNL

DeveloperArevon EnergyConstruction Dive · 2025-05-13
EPC contractorPrimoris Services Corp.Construction Dive · 2025-05-13
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-04-19

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.