Diver Solar
225.59 MW generation in Limestone, TX · In queue since September 2022 · Proposed COD January 2026
225.59 MW
Capacity
1
Components
Solar
4y 2m
In Queue
IA Executed
IA Phase
Signed Oct 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 1m
IA → COD
2y 3m
Total Duration
1y 1m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-01-16
Projected COD moved
4 times
Dec 2025 → Jan 2026
Net change
+1 months
first report to latest
Capacity
253 → 226 MW
changed in the reports
Latest stage
Commercial operation
last listed Jan 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Project built and became operational in August 2025
cleanview.coResearch sources and reasoning (4 recorded sources)
high confidence at research time
- cleanview.co/solar-farms/texas/68483/diver-solar-llc
- interconnection.fyi/project/ercot-25inr0105
- gem.wiki/Diver_solar_farm
- assets.comptroller.texas.gov/ch313/1900/1900-grosebeckisd-stetson-amendapp1.pdf
Commercial operation date: LBNL proposed COD was 2026-01-16, but Cleanview reports the project was built in August 2025, and both interconnection.fyi and Global Energy Monitor confirm the project is now operational. The project came online ~5 months earlier than the LBNL queue date.
Developer: LBNL filing entity is 'Diver Solar, LLC' (confirmed in Texas Comptroller Ch. 313 tax abatement documents). No parent company or operating entity distinct from the project LLC was identified in available sources, suggesting this may be a single-purpose project vehicle.
Status: Multiple independent sources (Cleanview, interconnection.fyi, Global Energy Monitor) confirm operational status as of late 2025/early 2026, superseding LBNL's 'Active' queue status.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Diver Solar SLF is a proposed 225.59 MW solar generation project located in Limestone County, Texas. The developer is Diver Solar. The project is interconnected within the ERCOT region under queue ID ERCOT-25INR0105, with an interconnection queue entry date of September 2, 2022, and a proposed commercial operation date of June 30, 2026. The project's Interconnection Agreement (IA) was executed on October 27, 2023.
The proposed project is linked to the existing Diver Solar, LLC operating plant (EIA plant ID 68483). Recent news coverage has discussed the project in the context of industry and grid developments.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jan 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Limestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Diver Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3384 St Johns - 3390 Jewett
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-19
View all articlesSolar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Diver Solar
Data-driven briefing on Diver Solar — fleet, generation, financial, and news signals.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.