Blue Skies BESS (ERCOT-25INR0046) — Project Summary

Queue ID
ERCOT-25INR0046
Capacity
306.26 MW
Technology
Battery
Status
active
Location
Hill, TX
Region
ERCOT
Developer
ACTX BESS Project LLC
IA Status
IA Executed

Blue Skies BESS

ERCOT-25INR0046BetaActiveBatteryERCOTLBNL + Live

306.26 MW storage in Hill, TX · In queue since May 2022 · Proposed COD April 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

306.26 MW

Capacity

1

Components

Battery

4y 6m

In Queue

IA Executed

IA Phase

Signed Jun 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 1m

IA → COD

3y 10m

Total Duration

2y 1m

Construction75%
Queue EntryMay 10, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJun 20, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-04-01

Queue history
25INR0046 · 54 monthly ERCOT reports, Apr 2022 – Sep 2026

Projected COD moved

3 times

May 2024 → Apr 2028

Net change

+47 months

first report to latest

Capacity

306 → 306 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 10, 2022
Interconnection agreement signedJun 20, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 1, 2028
From queue filing
Developer in saved assessment
Primergy
Filed as ACTX BESS Project LLC
Status at research time
Active
Active in the ERCOT queue with the interconnection agreement executed (SGIA filed at the Texas PUC in Aug 2024). Planned 2-hour BESS with no public sign of construction start; ercotqueue.com lists FIS as pending.
Financing
Not recorded

Milestones in this assessment

IA executedAug 14, 2024Latest in this assessment

ERCOT Standard Generation Interconnection Agreement between Lone Star Transmission, LLC and ACTX BESS Project LLC for Blue Skies BESS filed at the Texas PUC. LBNL records the IA date as 2024-06-20.

interchange.puc.texas.gov
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. primergypower.com/projects/blue-skies-bess
  2. blacklandtx.com/siting/blue-skies-bess/
  3. interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=1896
  4. ercotqueue.com/project/25INR0046
  5. infrasure.ai/project/ercot-25inr0046-blue-skies-bess

Commercial operation date: The only COD is the LBNL/ERCOT proposed date of 2028-04-01. The aggregator pages repeat it, and one of them also cites 2027-12-31. That page is built from queue data, so it is not an independent signal. No developer press release or news item gives a financing-backed target.

Developer: Primergy's own project page lists Blue Skies BESS (300 MW, 2-hour, Hill County, ERCOT North). The Blackland TX siting page names ACTX BESS Project LLC as the interconnecting entity and Primergy Solar as the developer, so the LLC is the project shell.

Status: LBNL shows active with IA executed. The PUC filings for the SGIA with Lone Star Transmission and Primergy's listing of the project as planned are consistent with that. No source shows withdrawal or construction.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Blue Skies BESS project is a proposed 306.26 MW battery storage project located in Hill County, Texas. Developed by ACTX BESS Project LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0046, with a queue entry date of May 10, 2022. The project's proposed commercial operation date is December 31, 2027.

The interconnection agreement for the Blue Skies BESS project has been executed as of August 12, 2024. The point of interconnection is the 68090 SAM SW 345kV substation. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Hill

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

ACTX BESS Project LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

68090 SAM SW 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.