Serrano Storage
185.59 MW storage in Maverick, TX · In queue since September 2023 · Proposed COD December 2027
185.59 MW
Capacity
1
Components
Battery
3y 2m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
Projected COD moved
2 times
Dec 2024 → Dec 2027
Net change
+36 months
first report to latest
Capacity
186 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue as 24INR0617
cleanview.coResearch sources and reasoning (3 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0617/serrano-storage
- interconnection.fyi/projects/state/TX
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
Commercial operation date: Only LBNL queue data provides a COD target of December 2027. No news coverage or press releases found for this specific Serrano Storage project in Maverick County, TX. Search results primarily returned unrelated projects (Longroad's Arizona Serrano Solar+BESS) and generic ERCOT queue aggregators.
Developer: No independent sources identify the parent company or operating entity behind Maverick ESS, LLC. The LLC name pattern suggests a project-specific vehicle, but without press releases or corporate announcements, the legal entity remains the only known identifier.
Status: LBNL status of 'Active' at Facility Study stage is consistent with queue position. Absence of news coverage suggests early-stage development with no major milestones reached yet.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Serrano Storage is a proposed 185.59 MW battery storage project located in Maverick County, Texas. The project, developed by Maverick ESS, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0617, with a queue entry date of September 23, 2023. The proposed commercial operation date is December 1, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The Serrano Storage project has been the subject of recent news coverage, with three articles detailing development and deal activity. The point of interconnection is the 8267 GANSO Substation at 138kV.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Maverick
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Maverick ESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8267 GANSO Substation 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.