Wetzel BESS
185.57 MW storage in Brown, TX · In queue since March 2023 · Proposed COD September 2028
185.57 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-09
Projected COD moved
2 times
Jun 2024 → Sep 2028
Net change
+51 months
first report to latest
Capacity
187 → 186 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0544/wetzel-bess
- img.electricalmarketing.com/files/base/ebm/electricalmarketing/document/2024/11/672d30a9d97ec15bd9ee2622-all_bess_projects.xlsx
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
- ercotqueue.com/developer/brown-ess-llc
Commercial operation date: LBNL queue filing shows proposed COD of September 2028. No news or press releases found to confirm or contradict this date. Cleanview aggregator site echoes the same September 2028 target from queue data.
Developer: LBNL filing entity is 'Brown ESS, LLC'. No press releases, corporate announcements, or news coverage found identifying a parent operating company. Search results only reference the LLC name from queue data.
Status: LBNL status is 'Active' at Facility Study stage. No news coverage of this Texas project found; search results mistakenly returned New York 'Wetzel Road' battery projects which are unrelated.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Wetzel BESS project is a proposed 185.57 MW battery storage project located in Brown County, Texas. Developed by Brown ESS, LLC, the project entered the ERCOT interconnection queue as entry 24INR0544 on March 27, 2023. The current interconnection status is listed as Facility Study, with a proposed commercial operation date of September 9, 2028.
The Wetzel BESS project has appeared in recent news coverage regarding energy storage development in Texas. It is a standalone battery project with no linked operating plant.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brown
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Brown ESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 1654 Zephyr – 1655 Brownwood Switch
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.