Medina City BESS (ERCOT-24INR0502) — Project Summary

Queue ID
ERCOT-24INR0502
Capacity
9.99 MW
Technology
Battery
Status
active
Location
Region
ERCOT
Developer
Regis Medina, LLC
IA Status
In Progress (unknown study)

Medina City BESS

ERCOT-24INR0502BetaActiveBatteryERCOTLBNL

9.99 MW storage in · In queue since November 2022 · Proposed COD March 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

9.99 MW

Capacity

1

Components

Battery

3y 8m

In Queue

In Progress (unknown study)

IA Phase

Signed Jan 2023

Interconnection

Queue → IA

2 months

IA → COD

3y 2m

Total Duration

2 months

Schedule

4 months past proposed COD

Construction38%
Queue EntryNov 29, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJan 18, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-03-02

About

The Medina City BESS project is a proposed 9.99 MW battery storage project located in Bandera County, Texas. Developed by Regis Medina, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-24INR0502 on November 29, 2022. The proposed commercial operation date is February 6, 2025.

The project's interconnection agreement is currently listed as "In Progress (unknown study)" with an agreement date of January 18, 2023. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

County

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Regis Medina, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Station Name (TDSP Station Code): MEDINA; Load/Load Transformer Name: L_MEDICI9_1Y; PTI BUS number: 7430; Voltage in kV (Transmission Level): 69kV_x000D_ Transformers: 3x 4000kVA 800VAC Δ - 12.47kVA Υ_x000D_ 12,000 MVA connected, Running load limited to 9.99 MW

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Medina City BESS
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.