Claire BESS (ERCOT-24INR0500) — Project Summary

Queue ID
ERCOT-24INR0500
Capacity
406.01 MW
Technology
Battery
Status
active
Location
Harris, TX
Region
ERCOT
Developer
BRP Blue Topaz 3, LLC
IA Status
Facility Study

Claire BESS

ERCOT-24INR0500BetaActiveBatteryERCOTLBNL + Live

406.01 MW storage in Harris, TX · In queue since February 2023 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

406.01 MW

Capacity

1

Components

Battery

3y 9m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 10m

Facilities Study50%
Queue EntryFeb 9, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-17

Queue history
24INR0500 · 45 monthly ERCOT reports, Jan 2023 – Sep 2026

Projected COD moved

3 times

Jun 2024 → Dec 2027

Net change

+42 months

first report to latest

Capacity

406 MW

unchanged in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 9, 2023
Facilities study approvedJan 24, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 17, 2027
From queue filing
Developer in saved assessment
BRP Blue Topaz 3, LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue at Facility Study stage, with no executed IA; proposed 406 MW standalone battery at Cedar Bayou 138kV, Harris County.
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0500/claire-bess
  2. interconnection.fyi/project/ercot-24inr0500
  3. infrasure.ai/project/ercot-24inr0500-claire-bess
  4. quicksandcheck.com/texas/harris-county/
  5. groundtrace.io/developers/brp-blue-topaz-3-llc-3ffu5lmb7rwmg

Commercial operation date: Only LBNL gives a specific date (2027-12-17). Cleanview and Quicksand Check show 'December 2027', but they appear to be derived from the same ERCOT/LBNL queue data, so they are not independent confirmation. No developer press release or news item gives a different target.

Developer: Queue aggregators (Infrasure, Groundtrace, Quicksand Check) all list BRP Blue Topaz 3, LLC. The news-extracted 'Enlight Renewable Energy' comes from a March 2025 debt-financing article about other US solar/BESS assets, and no live search result links Enlight to Claire BESS. I did not adopt it, and the parent behind the BRP shell is unidentified.

Status: LBNL and the aggregators (interconnection.fyi, Quicksand Check) show the project as active and in study. There is no evidence of withdrawal, construction start or an executed IA.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Claire BESS project is a proposed 406.01 MW battery storage project located in Harris County, Texas. Developed by BRP Blue Topaz 3, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-24INR0500. It entered the interconnection queue on February 9, 2023, with a proposed commercial operation date of December 17, 2027. The project's interconnection status is currently in the Facility Study phase.

The Claire BESS project has been the subject of recent news coverage, with six articles published about it. These articles cover topics such as deals, grid infrastructure, and project development.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Harris

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BRP Blue Topaz 3, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

40011 Cedar Bayou 138kV

Data Source

LBNL + Live

DeveloperEnlight Renewable EnergyreNews - Renewable Energy News · 2025-03-31
TransactionDebt financingreNews - Renewable Energy News · 2025-03-31
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
MEDIUM
Nearest Node (Estimated)
CBY_CBY_G1
POI Substation
Cedar Bayou Plant Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-03-14

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.