DOS RIOS ENERGY STORAGE SLF (ERCOT-24INR0476) — Project Summary

Queue ID
ERCOT-24INR0476
Capacity
164.5 MW
Technology
Battery
Status
active
Location
Milam, TX
Region
ERCOT
Developer
DOS RIOS SOLAR, LLC
IA Status
IA Executed

DOS RIOS ENERGY STORAGE SLF

ERCOT-24INR0476BetaActiveBatteryERCOTLBNL

164.5 MW storage in Milam, TX · In queue since November 2022 · Proposed COD March 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

164.5 MW

Capacity

1

Components

Battery

4 years

In Queue

IA Executed

IA Phase

Signed May 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 6m

IA → COD

1y 10m

Total Duration

2y 6m

Construction75%
Queue EntryNov 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 13, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-03-15

Queue history
24INR0476 · 36 monthly ERCOT reports, Mar 2023 – Feb 2026

Projected COD moved

2 times

Oct 2025 → Oct 2027

Net change

+24 months

first report to latest

Capacity

0 → 165 MW

changed in the reports

Latest stage

Cancelled

last listed Feb 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 15, 2022
Facilities study approvedOct 24, 2024
Interconnection agreement signedMay 13, 2025
CancelledMar 30, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Mar 2027
From queue filing
Developer in saved assessment
DOS RIOS SOLAR, LLC
From queue filing
Status at research time
Active
Active — IA executed May 2025, targeting 2027 COD per ERCOT capacity planning documents
Financing
Not recorded

Milestones in this assessment

IA executedMay 13, 2025

Interconnection Agreement executed per LBNL queue data, confirmed in ERCOT capacity planning

ercot.com
COD targetMar 2027Latest in this assessment

Target COD March 2027 per Texas PUC generating plants report and ERCOT capacity charts

ftp.puc.texas.gov
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. ercot.com/files/docs/2025/12/04/Capacity-Changes-by-Fuel-Type-Charts_November_2025_PlannedMonthly.xlsx
  2. ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
  3. ercot.com/files/docs/2025/12/05/MORA_February2026.pdf
  4. ercot.com/files/docs/2026/02/05/Capacity-Changes-by-Fuel-Type-Charts_January_2026.xlsx

Commercial operation date: LBNL queue shows 2027-03-15 COD. Multiple ERCOT capacity charts from 2025-2026 consistently list '2027' as the target year. No press releases or news articles found to provide a more recent developer-stated target.

Developer: LBNL filing entity is 'DOS RIOS SOLAR, LLC'. No press releases, corporate announcements, or news coverage found to identify a parent operating company. The entity name suggests a project-specific LLC, but without additional sources, we cannot confirm a separate parent developer.

Status: LBNL shows 'active' status with IA executed 2025-05-13. ERCOT capacity charts through December 2025 consistently list the project as planned for 2027. One third-party aggregator (interconnection.fyi) shows 'Withdrawn' but this contradicts official ERCOT sources and the executed IA.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The DOS RIOS ENERGY STORAGE SLF project is a proposed 164.5 MW battery storage project located in Milam County, Texas. The developer is DOS RIOS SOLAR, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0476, with a queue entry date of November 15, 2022. The proposed commercial operation date is October 15, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.

The project consists of 164.5 MW of battery storage capacity. It is interconnected at the TAP 69 KV 61 BRANCHVILLE -- 65 SILVER CITY point of interconnection. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Feb 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Milam

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

DOS RIOS SOLAR, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

TAP 69 KV 61 BRANCHVILLE -- 65 SILVER CITY

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
Branchville Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.