Longfellow BESS II (ERCOT-24INR0455) — Project Summary

Queue ID
ERCOT-24INR0455
Capacity
105.75 MW
Technology
Solar+Battery
Status
active
Location
Pecos, TX
Region
ERCOT
Developer
CENTURY GAS PROCESSING, LLC
IA Status
IA Executed

Longfellow BESS II

ERCOT-24INR0455BetaActiveBatteryBatteryERCOTLBNL + Live

105.75 MW generation in Pecos, TX · In queue since November 2022 · Proposed COD March 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

105.75 MW

Capacity

1

Components

Battery

4 years

In Queue

IA Executed

IA Phase

Signed Apr 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 5m

IA → COD

2y 11m

Total Duration

2y 5m

Construction75%
Queue EntryNov 7, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementApr 15, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-03-30

Queue history
24INR0455 · 42 monthly ERCOT reports, Apr 2023 – Sep 2026

Projected COD moved

5 times

Dec 2024 → Mar 2028

Net change

+39 months

first report to latest

Capacity

106 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 7, 2022
Facilities study approvedDec 17, 2025
Interconnection agreement signedApr 15, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Nov 2026
Differs from queue: Mar 30, 2028From queue filing
Developer in saved assessment
SolarMax Technology Inc
Filed as CENTURY GAS PROCESSING, LLC
Status at research time
IA Executed
IA Executed (2025-04-15) — EPC contract awarded to SolarMax Technology in August 2025, construction phase underway
Financing
Secured
$127.3M EPC contract awarded to SolarMax Technology Inc, announced August 2025

Milestones in this assessment

IA executedApr 15, 2025

Interconnection Agreement executed with ERCOT

renewablesnow.com
Financing closeAug 2025

SolarMax awarded $127.3M EPC contract for 430 MWh battery system

stocktitan.net
COD targetNov 2026Latest in this assessment

Target commercial operation date per ERCOT filings

ftp.puc.texas.gov
Research sources and reasoning (5 recorded sources)

high confidence at research time

  1. renewablesnow.com/news/solarmax-to-build-invest-in-430-mwh-battery-project-in-texas-1279705/
  2. stocktitan.net/news/SMXT/solar-max-technology-awarded-127-3-million-epc-contract-for-430-m-wh-bdpoh357ud1h.html
  3. energy-storage.news/texas-ascend-analytics-optimises-50mwh-for-adapture-solarmax-to-build-430mwh-project/
  4. tradingview.com/news/tradingview:b6aa80091aa5a:0-solarmax-technology-2025-10-k-91m-revenue-0-13-eps/
  5. ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls

Commercial operation date: LBNL proposed COD of 2026-11-30 is the only explicit date available. No news sources provide an updated or conflicting COD target for this specific project.

Developer: LBNL filing entity is CENTURY GAS PROCESSING, LLC (likely a project SPV). Multiple August 2025 sources confirm SolarMax Technology Inc (NASDAQ:SMXT) was awarded a $127.3M EPC contract to build a 430 MWh battery project in Texas matching this project's profile and timeline.

Status: LBNL shows IA executed on 2025-04-15. SolarMax's August 2025 contract announcement and subsequent 10-K filings referencing large-scale EPC battery projects in Texas confirm active development.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Longfellow BESS II project is a proposed 105.75 MW battery storage project located in Pecos County, Texas. The developer is CENTURY GAS PROCESSING, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0455, with a queue entry date of November 7, 2022. The proposed commercial operation date is November 30, 2026, and the interconnection agreement status is Facility Study.

The project consists solely of battery storage, with a total capacity of 105.75 MW. The point of interconnection is the 38432 TNCENTRY2_1 138 KV substation. The project is listed as active in the interconnection queue.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Pecos

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

CENTURY GAS PROCESSING, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

38432 TNCENTRY2_1 138 KV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.