Briefing/projectactive
Longfellow BESS II is a 106 MW Solar+Battery project in Texas, currently active.
CENTURY GAS PROCESSING, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-11-30.
- Queue ID
- ERCOT-24INR0455
- Location
- Pecos, Texas
- Technology
- Solar+Battery
- Developer
- CENTURY GAS PROCESSING, LLC
- Market / region
- ERCOT
- Point of interconnection
- 38432 TNCENTRY2_1 138 KV
What stands out
1
Longfellow BESS II is a 106 MW Solar+Battery project in Texas with status active.
2
CENTURY GAS PROCESSING, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2026-11-30.
Market and operating context
- Queue date
- 2022-11-07
- Proposed COD
- 2026-11-30
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.