Query
Longfellow BESS II
Type
Entity Briefing
Entity
Longfellow BESS II
State
TN
Technology
battery
Generated
2026-10-12T03:58:47.942Z

Briefing on Longfellow BESS II

Entity Briefing
Generated Oct 12, 2026·Dataset freshness not reported
106 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2026-11-30
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Longfellow BESS II is a 106 MW Solar+Battery project in Texas, currently active.

CENTURY GAS PROCESSING, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-11-30.

Queue ID
ERCOT-24INR0455
Location
Pecos, Texas
Technology
Solar+Battery
Developer
CENTURY GAS PROCESSING, LLC
Market / region
ERCOT
Point of interconnection
38432 TNCENTRY2_1 138 KV

What stands out

1

Longfellow BESS II is a 106 MW Solar+Battery project in Texas with status active.

2

CENTURY GAS PROCESSING, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-11-30.

Market and operating context

Queue date
2022-11-07
Proposed COD
2026-11-30
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Longfellow BESS II — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0455
LocationPecos, Texas
TechnologySolar+Battery
DeveloperCENTURY GAS PROCESSING, LLC
Market / regionERCOT
Point of interconnection38432 TNCENTRY2_1 138 KV
Queue date2022-11-07
Proposed COD2026-11-30