Longfellow Solar I
178.2 MW hybrid in Pecos, TX · In queue since November 2022 · Proposed COD December 2028
178.2 MW
Capacity
1
Components
Solar
4 years
In Queue
IA Executed
IA Phase
Signed Apr 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 5m
IA → COD
3y 8m
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2028-12-31
Projected COD moved
3 times
Dec 2024 → Dec 2028
Net change
+48 months
first report to latest
Capacity
178 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with ERCOT
ercotqueue.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- ercotqueue.com/project/24INR0452
- ercotqueue.com/developer/century-gas-processing-llc
- interconnection.fyi/project/ercot-24inr0452
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-db7
- ercot.com/files/docs/2025/06/06/Capacity-Changes-by-Fuel-Type-Charts_May_2025.xlsx
Commercial operation date: LBNL queue shows proposed COD of 2028-12-31. No press releases or news articles provide an updated target date. Reddit speculation mentioned Jan 2026 for related projects but no authoritative source confirms a different date for Longfellow Solar I specifically.
Developer: CENTURY GAS PROCESSING, LLC appears consistently across all sources as both the filing entity and operating entity. No parent company or shell-LLC structure is evident. Reddit posts speculate about SOS Limited connection to the broader Longfellow project portfolio, but no authoritative sources confirm ownership by a different parent entity.
Status: LBNL shows 'active' with IA executed 2025-04-15. ERCOTqueue.com confirms 'IA, FIS pending' status as of May 2026. No construction milestones or groundbreaking announcements found in search results.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Longfellow Solar I is a proposed 178.2 MW solar generation project located in Pecos County, Texas. The project, developed by CENTURY GAS PROCESSING, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0452, with a queue entry date of November 7, 2022. Its proposed commercial operation date is June 30, 2027, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 178.2 MW of solar photovoltaic generation. It is planned to connect to the 38431 TNCENTRY1_1 138 KV point of interconnection. The Longfellow Solar I project has appeared in recent news coverage regarding energy development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CENTURY GAS PROCESSING, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
38431 TNCENTRY1_1 138 KV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.