PSE Gongora Hill TX Storage
200 MW storage in Starr, TX · In queue since February 2023 · Proposed COD June 2028
200 MW
Capacity
1
Components
Battery
3y 9m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
Projected COD moved
5 times
Oct 2024 → Jun 2028
Net change
+44 months
first report to latest
Capacity
201 → 200 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Proposed completion date updated from Dec 30, 2026 to July 30, 2027 per ERCOT interconnection study revision
interconnectionfyi.substack.comResearch sources and reasoning (3 recorded sources)
medium confidence at research time
- interconnectionfyi.substack.com/p/interconnectionfyi-weekly-digest
- cleanview.co/power-projects/developers/puresky-energy
- ercotqueue.com/project/24INR0446
Commercial operation date: Interconnection.fyi weekly digest from Dec 9, 2024 reports proposed completion changed from Dec 30, 2026 to July 30, 2027, which is 11 months earlier than LBNL's June 30, 2028 date. This reflects a more recent interconnection study update.
Developer: LBNL lists 'PureSky Development Inc' while Cleanview and other trackers consistently refer to the parent operating company as 'Puresky Energy'. The LBNL entity appears to be the development subsidiary rather than a project-specific shell LLC.
Status: LBNL status 'active' with 'Facility Study' IA status is confirmed by all tracking sources. No evidence of construction activity, financing, or permitting milestones.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The PSE Gongora Hill TX Storage project is a proposed 200 MW battery energy storage system in Starr County, Texas. Developed by PureSky Development Inc., the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0446, with a queue entry date of February 27, 2023. The proposed commercial operation date is June 30, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for the project is Tap 138kV 8796 Roma _x0013_ 7870 Escobares. The development has appeared in recent news coverage regarding energy storage projects in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Starr
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
PureSky Development Inc
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 8796 Roma – 7870 Escobares
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.