Hollow Branch Creek Storage (ERCOT-24INR0423) — Project Summary

Queue ID
ERCOT-24INR0423
Capacity
460 MW
Technology
Solar+Battery
Status
active
Location
Leon, TX
Region
ERCOT
Developer
Hollow Branch Creek Solar LLC
IA Status
Facility Study

Hollow Branch Creek Storage

ERCOT-24INR0423BetaActiveBatteryBatteryERCOTLBNL

460 MW generation in Leon, TX · In queue since September 2022 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

460 MW

Capacity

1

Components

Battery

4y 2m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 3m

Facilities Study50%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Queue history
24INR0423 · 39 monthly ERCOT reports, Sep 2022 – Feb 2026

Projected COD moved

3 times

Dec 2024 → Dec 2027

Net change

+36 months

first report to latest

Capacity

0 → 460 MW

changed in the reports

Latest stage

Cancelled

last listed Feb 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 2, 2022
Facilities study approvedOct 3, 2024
CancelledMar 23, 2026
On ERCOT's inactive listJan 2025 – Mar 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Jun 30, 2028
Differs from queue: Dec 31, 2027
Developer in saved assessment
Parliament Energy
Filed as Hollow Branch Creek Solar LLC
Status at research time
Active
Active in the ERCOT queue (Facility Study per LBNL). The sibling solar entry 24INR0422 shows an IA executed in Oct 2024, and GEM lists the project as pre-construction. Separate SLF queue entries (24INR0171, 24INR0443) are withdrawn and look like superseded duplicates.
Financing
Not recorded
Unverified. Renewables Now reports Parliament Energy closed USD 747m in financing for a Texas solar project about 3 months ago, but the snippet does not name Hollow Branch, so it cannot be tied to this project.

Milestones in this assessment

IA executedOct 22, 2024

Interconnection Agreement executed for the companion solar entry 24INR0422 (same 460 MW Hollow Branch Creek project).

infrasure.ai
COD targetJun 30, 2028Latest in this assessment

Parliament Energy targets Hollow Branch completion in Q2 2028 (Infrasure lists 2028-06-30).

parliamentenergy.com
Research sources and reasoning (6 recorded sources)

medium confidence at research time

  1. parliamentenergy.com/hollow-branch
  2. infrasure.ai/project/ercot-24inr0422-hollow-branch-creek-solar
  3. infrasure.ai/project/ercot-24inr0423-hollow-branch-creek-storage
  4. cleanview.co/power-projects/planned/solar-farms/texas/24INR0422/hollow-branch-creek-solar-
  5. gem.wiki/Hollow_Branch_Creek_Solar
  6. renewablesnow.com/news/parliament-energy-secures-usd-747m-in-financing-for-texas-solar-project-1297143/

Commercial operation date: Parliament Energy's project page says Hollow Branch (598MWdc/460MWac) is "targeted for completion in Q2 2028", and Infrasure lists a proposed COD of 2028-06-30 for the companion solar queue entry 24INR0422. That is about 6 months after LBNL's 2027-12-31, so it is a slight slip rather than a multi-year gap. The dates come from the solar sibling entry, not this storage entry directly.

Developer: The LBNL filing entity is a project LLC. Parliament Energy (an EnCap Energy Transition Fund II / Mercuria platform) publishes the Hollow Branch project (460MWac, Texas) on its own website, which matches the capacity and name. No acquisition or transfer history was found.

Status: LBNL's 'active' status is consistent with the live research: the project is still being developed and targets a 2028 COD, and no withdrawal of this specific queue ID (24INR0423) was found. The county differs between sources (Leon vs Madison), probably because the site is near the county line.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Hollow Branch Creek Storage project is a proposed 460 MW battery energy storage system in Leon County, Texas. The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0423. Its proposed commercial operation date is December 31, 2027.

The project is currently listed as active in the interconnection queue. Recent news coverage indicates public interest in the development of large-scale battery storage projects within the ERCOT region.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Feb 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Leon

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Hollow Branch Creek Solar LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Jewett – Singleton 345 kV [PTI Bus # 3390 – 44645]

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.