High Plains Storage
157.7 MW storage in Harris, TX · In queue since September 2022 · Proposed COD May 2028
157.7 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-30
Projected COD moved
5 times
Jun 2025 → May 2028
Net change
+35 months
first report to latest
Capacity
150 → 158 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Proposed completion date updated from Oct 2025 to Oct 2026
interconnectionfyi.substack.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0419/high-plains-storage
- interconnection.fyi/project/ercot-24inr0419
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
- interconnectionfyi.substack.com/p/interconnectionfyi-weekly-digest
- ercotqueue.com/project/24INR0419
Commercial operation date: Interconnection.fyi weekly digest (Dec 2024) reports proposed completion changed from Oct 2025 to Oct 2026, reflecting a 1.5-year acceleration from LBNL's May 2028 date. This is a more recent update than the LBNL queue snapshot.
Developer: No alternative developer name found in research. ROBP Holdings, LLC appears consistently across LBNL, Cleanview, and AWS buildout pipeline sources with no parent company identified.
Status: LBNL status 'active' confirmed by multiple queue-tracking sources. Interconnection.fyi reports COD timeline adjustment in Dec 2024, indicating ongoing project development.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The High Plains Storage project is a proposed 157.7 MW battery energy storage system located in Harris County, Texas. The project, developed by ROBP Holdings, LLC, is currently in the ERCOT interconnection queue as entry ERCOT-24INR0419, with a queue entry date of September 2, 2022. Its proposed commercial operation date is May 30, 2028, and its interconnection status is currently in the Facility Study phase.
The High Plains Storage development project has been mentioned in recent news coverage related to the energy industry.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ROBP Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
45880 Hockley 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Hockley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.