ELECTRODE BESS
150 MW storage in Upton, TX · In queue since July 2022 · Proposed COD December 2027
150 MW
Capacity
1
Components
Battery
4 years
In Queue
Facility Study
IA Phase
COD target: 2027
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The ELECTRODE BESS project is a proposed 150 MW battery storage project located in Upton County, Texas. Developed by CED Development Inc., the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0393, with a queue entry date of July 25, 2022.
The proposed commercial operation date for ELECTRODE BESS is December 31, 2027. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Castillo Substation, Bus number 76040.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CED Development Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76040 Castillo 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about ELECTRODE BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.