Soda Lake BESS 2 SLF (ERCOT-24INR0383) — Project Summary

Queue ID
ERCOT-24INR0383
Capacity
205.35 MW
Technology
Solar+Battery
Status
active
Location
Crane, TX
Region
ERCOT
Developer
Crane II Solar Electric, LLC
IA Status
Facility Study

Soda Lake BESS 2 SLF

ERCOT-24INR0383BetaActiveBatteryBatteryERCOTLBNL + Live

205.35 MW generation in Crane, TX · In queue since September 2022 · Proposed COD October 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

205.35 MW

Capacity

1

Components

Battery

4y 2m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 1m

Facilities Study50%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-30

Queue history
24INR0383 · 28 monthly ERCOT reports, Aug 2022 – Sep 2026

Projected COD moved

2 times

Nov 2024 → Oct 2028

Net change

+47 months

first report to latest

Capacity

200 → 205 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 2, 2022
Interconnection agreement signedAug 21, 2026
On ERCOT's inactive listJul 2023 – Apr 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Dec 1, 2027
Differs from queue: Oct 30, 2028From queue filing
Developer in saved assessment
Headwater Energy
Filed as Crane II Solar Electric, LLC
Status at research time
Active
Active — Facility Study stage, no IA executed yet. ERCOTqueue estimates 5% build probability given lack of IA progress.
Financing
Not recorded
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. interconnection.fyi/project/ercot-24inr0383
  2. cleanview.co/power-projects/developers/headwater-energy
  3. ercotqueue.com/project/24INR0383
  4. ercotqueue.com/developer/crane-ii-solar-electric-llc

Commercial operation date: Only LBNL queue data provides a COD target of December 2027. No independent news sources or press releases confirm or update this date.

Developer: LBNL filing uses project LLC 'Crane II Solar Electric, LLC'. Cleanview pipeline database attributes this project to Headwater Energy as the operating developer/parent company.

Status: LBNL shows 'active' status at Facility Study stage with no IA date. ERCOTqueue corroborates this with 'No IA' designation and low build-chance estimate.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Soda Lake BESS 2 SLF (queue ID ERCOT-24INR0383) is a proposed energy development project in Crane County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The developer is Crane II Solar Electric, LLC. The project is classified in the interconnection queue as a Solar+Battery generation project with a total capacity of 205.35 MW. Its listed components consist solely of battery storage, totaling 205.35 MW, and no separate solar capacity is specified in the queue data. The project would connect to the grid at the 138 kV Soda Lake substation (#76026).

The project entered the ERCOT interconnection queue on September 2, 2022, and remains in active status. It is in the Facility Study phase of the interconnection process, and its proposed commercial operation date is October 30, 2028.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Crane

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Crane II Solar Electric, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

138 kV Soda Lake (#76026)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.