Query
Soda Lake BESS 2 SLF
Type
Entity Briefing
Entity
Soda Lake BESS 2 SLF
State
TN
Technology
battery
Generated
2026-10-19T20:11:40.963Z

Briefing on Soda Lake BESS 2 SLF

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
205 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-12-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Soda Lake BESS 2 SLF is a 205 MW Solar+Battery project in Texas, currently active.

Crane II Solar Electric, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-12-01.

Queue ID
ERCOT-24INR0383
Location
Crane, Texas
Technology
Solar+Battery
Developer
Crane II Solar Electric, LLC
Market / region
ERCOT
Point of interconnection
138 kV Soda Lake (#76026)

What stands out

1

Soda Lake BESS 2 SLF is a 205 MW Solar+Battery project in Texas with status active.

2

Crane II Solar Electric, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-12-01.

Market and operating context

Queue date
2022-09-02
Proposed COD
2027-12-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Soda Lake BESS 2 SLF — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0383
LocationCrane, Texas
TechnologySolar+Battery
DeveloperCrane II Solar Electric, LLC
Market / regionERCOT
Point of interconnection138 kV Soda Lake (#76026)
Queue date2022-09-02
Proposed COD2027-12-01