Anatole Renewable Energy Storage
207.82 MW storage in Henderson, TX · In queue since June 2022 · Proposed COD June 2027
207.82 MW
Capacity
1
Components
Battery
4y 1m
In Queue
IA Executed
IA Phase
Signed May 2024
Queue → IA
1y 11m
IA → COD
3y 1m
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-06-01
The Anatole Renewable Energy Storage project is a proposed 207.82 MW battery storage project located in Henderson County, Texas. The developer is Eustace Storage LLC. It is interconnected within the ERCOT region under queue ID ERCOT-24INR0355, with a queue entry date of June 2, 2022, and a proposed commercial operation date of March 31, 2027.
The project's Interconnection Agreement (IA) has been executed as of May 10, 2024. The point of interconnection is the Eustace Southeast 138kV Substation (Bus# 6951), owned by Rayburn Electric Cooperative.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Henderson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Eustace Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
(Bus# 6951) Eustace Southeast 138kV Substation (owned by Rayburn Electric Cooperative)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Southeast Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Anatole Renewable Energy StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.