Forts Trail BESS
208.82 MW generation in Taylor, TX · In queue since June 2022 · Proposed COD March 2029
208.82 MW
Capacity
1
Components
Battery
4y 5m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-02
Projected COD moved
8 times
Jun 2024 → Mar 2029
Net change
+57 months
first report to latest
Capacity
0 → 209 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Proposed completion date updated from June 2026 to July 2027
interconnectionfyi.substack.comResearch sources and reasoning (3 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0341/forts-trail-bess
- interconnectionfyi.substack.com/p/interconnectionfyi-weekly-digest
- interconnection.fyi/project/ercot-24inr0341
Commercial operation date: Interconnection.fyi reported in Dec 2024 that proposed completion changed from June 2026 to July 2027, which is 1 year earlier than LBNL's July 2028 date. The research source reflects a more recent project update than the LBNL snapshot.
Developer: Only the LBNL filing entity 'JC Central Bluff, LLC' is available. No press releases, news articles, or corporate announcements identify the parent operating company behind this project LLC.
Status: LBNL status is 'active' in Facility Study. No news coverage of this specific project exists to indicate construction start, financing, or other advancement beyond interconnection studies.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Forts Trail BESS project is a proposed 200.93 MW battery storage project located in Taylor County, Texas. Developed by JC Central Bluff, LLC, the project is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-24INR0341 on June 2, 2022. The proposed commercial operation date is July 25, 2028, and the project's interconnection status is currently in the Facility Study phase.
The Forts Trail BESS project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Taylor
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
JC Central Bluff, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
11406 Central Bluff Switch 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Central
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Forts Trail BESS
Data-driven briefing on Forts Trail BESS — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.