Erika Solar (ERCOT-24INR0303) — Project Summary

Queue ID
ERCOT-24INR0303
Capacity
200.5 MW
Technology
Solar+Battery
Status
active
Location
Kaufman, TX
Region
ERCOT
Developer
Erika Solar, LLC
IA Status
IA Executed

Erika Solar

ERCOT-24INR0303BetaActiveSolarBatteryERCOTLBNL + Live

200.5 MW hybrid in Kaufman, TX · In queue since July 2022 · Proposed COD November 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

200.5 MW

Capacity

1

Components

Solar

4y 4m

In Queue

IA Executed

IA Phase

Signed Oct 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 3m

IA → COD

3y 1m

Total Duration

1y 3m

Construction75%
Queue EntryJul 25, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 12, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-11-25

Queue history
24INR0303 · 51 monthly ERCOT reports, Jul 2022 – Sep 2026

Projected COD moved

5 times

Aug 2024 → Nov 2026

Net change

+27 months

first report to latest

Capacity

204 → 201 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJul 25, 2022
Facilities study approvedSep 15, 2025
Interconnection agreement signedOct 12, 2023
Approved for energizationAug 14, 2026
Approved for synchronizationAug 27, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Jul 23, 2027
Differs from queue: Nov 25, 2026
Developer in saved assessment
Erika Solar, LLC
From queue filing
Status at research time
Active
Active — IA executed Oct 2023, COD target updated to July 2027 per April 2025 queue revision
Financing
Not recorded

Milestones in this assessment

IA executedOct 12, 2023

Interconnection Agreement executed with ERCOT

interconnection.fyi
COD targetJul 23, 2027Latest in this assessment

Proposed completion date updated from June 30, 2026 to July 23, 2027

interconnectionfyi.substack.com
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. interconnection.fyi/project/ercot-24inr0303
  2. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-ad5
  3. renewablesinfo.org/project/ercot-27inr0531-erika-bess
  4. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&ItemMatch=Equal&DocumentType=ALL&SortBy=ItemType&SortOrder=Ascending&Page=2

Commercial operation date: LBNL proposed COD was 2027-06-30, but Interconnection.fyi reported on April 14, 2025 that the proposed completion changed to July 23, 2027 — a 1-month slip reflecting updated developer timeline.

Developer: No parent company or operating entity identified in search results. LBNL filing entity 'Erika Solar, LLC' appears to be the actual developer, not a shell LLC. No press releases or corporate announcements found to indicate a larger parent organization.

Status: LBNL status is 'active' with IA executed in October 2023. Interconnection.fyi confirms the project remains active with an updated COD target as of April 2025, indicating ongoing development.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Erika Solar project is a proposed 204.08 MW solar generation facility in Kaufman County, Texas. The project, developed by Erika Solar, LLC, is interconnected within the ERCOT region under queue ID ERCOT-24INR0303. It entered the interconnection queue on July 25, 2022, with a proposed commercial operation date of June 30, 2027.

The project's Interconnection Agreement (IA) has been executed as of October 12, 2023. The point of interconnection is Tap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432). The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Kaufman

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Erika Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.