Briefing on Erika Solar

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
201 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-06-30
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Erika Solar is a 201 MW Solar+Battery project in Texas, currently active.

Erika Solar, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-06-30.

Queue ID
ERCOT-24INR0303
Location
Kaufman, Texas
Technology
Solar+Battery
Developer
Erika Solar, LLC
Market / region
ERCOT
Point of interconnection
Tap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432)

What stands out

1

Erika Solar is a 201 MW Solar+Battery project in Texas with status active.

2

Erika Solar, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2027-06-30.

Market and operating context

Queue date
2022-07-25
Proposed COD
2027-06-30
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Erika Solar — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0303
LocationKaufman, Texas
TechnologySolar+Battery
DeveloperErika Solar, LLC
Market / regionERCOT
Point of interconnectionTap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432)
Queue date2022-07-25
Proposed COD2027-06-30