Pintail Pass BESS
207.25 MW storage in San Patricio, TX · In queue since April 2022 · Proposed COD February 2026
207.25 MW
Capacity
1
Components
Battery
4y 7m
In Queue
IA Executed
IA Phase
Signed May 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 1m
IA → COD
2y 9m
Total Duration
1y 1m
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-02-15
Projected COD moved
10 times
Jun 2024 → Aug 2026
Net change
+26 months
first report to latest
Capacity
201 → 207 MW
changed in the reports
Latest stage
Commercial operation
last listed Aug 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Aug 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Lydian Energy closed $233M financing for three Texas BESS including Pintail Pass, equipment by CATL
energy-storage.newsResearch sources and reasoning (5 recorded sources)
high confidence at research time
- energy-storage.news/lydian-energy-closes-us233-million-financing-for-three-texas-bess-provided-by-catl/
- cleanview.co/planned-battery-projects/TX/24INR0302/pintail-pass-bess
- cleanview.co/power-projects/planned/battery-storage-projects/texas
- ercot.com/files/docs/2024/06/06/Capacity-Changes-by-Fuel-Type-Charts_May_2024_PlannedMonthly.xlsx
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/09/26/ERCOT_BESS_Buildout_Report_August_2024.xlsx
Commercial operation date: LBNL proposed COD of June 2026 is corroborated by multiple independent sources including Cleanview and ERCOT's May 2024 capacity chart, which lists 2025 but likely reflects earlier data. No contradictory recent announcements found.
Developer: LBNL filing entity is 'Pintail Pass BESS, LLC' (project SPV registered May 2022). Cleanview and Energy-Storage.News identify the operating parent as Lydian Energy, which closed $233M financing for three Texas BESS projects in July 2025.
Status: LBNL status 'Active' with IA executed May 2023 is accurate. Lydian Energy's July 2025 financing close for three Texas BESS (including Pintail Pass) indicates project is advancing toward construction.
About
Generated Apr 10, 2026 · Predates Aug 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Pintail Pass BESS is a proposed 207.25 MW battery storage project in San Patricio County, Texas. Developed by Pintail Pass BESS, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-24INR0302. The project entered the queue on April 18, 2022, with a proposed commercial operation date of March 31, 2026.
The project's Interconnection Agreement (IA) was executed on May 16, 2023. Pintail Pass BESS is linked to the existing Pintail BESS operating plant (EIA plant ID 68582). The point of interconnection is the 8249 ANGSTROM 345KV substation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Aug 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
San Patricio
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pintail Pass BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8249 ANGSTROM 345KV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Pintail Pass BESS
Data-driven briefing on Pintail Pass BESS — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.