Briefing on Pintail Pass BESS

Entity Briefing
Generated Oct 18, 2026·Dataset freshness not reported
207 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2026-06-09
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Pintail Pass BESS is a 207 MW Battery project in Texas, currently active.

Pintail Pass BESS, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-06-09.

Queue ID
ERCOT-24INR0302
Location
San Patricio, Texas
Technology
Battery
Developer
Pintail Pass BESS, LLC
Market / region
ERCOT
Point of interconnection
8249 ANGSTROM 345KV

What stands out

1

Pintail Pass BESS is a 207 MW Battery project in Texas with status active.

2

Pintail Pass BESS, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-06-09.

Market and operating context

Queue date
2022-04-18
Proposed COD
2026-06-09
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Pintail Pass BESS — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0302
LocationSan Patricio, Texas
TechnologyBattery
DeveloperPintail Pass BESS, LLC
Market / regionERCOT
Point of interconnection8249 ANGSTROM 345KV
Queue date2022-04-18
Proposed COD2026-06-09