Leighton Solar SLF
183 MW generation in Limestone, TX · In queue since May 2022 · Proposed COD December 2027
183 MW
Capacity
1
Components
Solar
4y 6m
In Queue
IA Executed
IA Phase
Signed May 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2 years
IA → COD
3y 7m
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-06
Projected COD moved
7 times
Nov 2024 → Dec 2027
Net change
+37 months
first report to latest
Capacity
180 → 181 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Proposed commercial operation date per latest ERCOT capacity charts
ercot.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- interconnection.fyi/project/ercot-24inr0298
- cleanview.co/power-projects/developers/rkb-energy
- ercotqueue.com/developer/lavender-solar-llc
- ercot.com/files/docs/2026/02/05/Capacity-Changes-by-Fuel-Type-Charts_January_2026.xlsx
- ercot.com/files/docs/2024/12/06/Capacity%20Changes%20by%20Fuel%20Type%20Charts_November_2024.xlsx
Commercial operation date: LBNL queue shows September 2027 COD. ERCOT capacity charts from late 2024 showed 2026 target, but more recent ERCOT charts (Nov 2025, Jan 2026) confirm 2027, indicating a ~1-year slip that has now stabilized in official filings.
Developer: LBNL filing uses 'Lavender Solar LLC' (project SPV). Cleanview's RKB Energy pipeline page lists Leighton Solar SLF as one of RKB's top projects, identifying RKB Energy as the operating developer behind the Lavender Solar shell entity.
Status: LBNL shows IA executed 2024-05-28. ERCOT queue tracker confirms project is at IA stage with FIS pending, consistent with active pre-construction phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Leighton Solar SLF project is a proposed 183 MW solar generation project located in Limestone County, Texas. Developed by Lavender Solar LLC, the project is in the ERCOT interconnection queue as entry ERCOT-24INR0298, with a queue entry date of May 11, 2022. The proposed commercial operation date is September 1, 2027.
The project's interconnection agreement has been executed as of May 28, 2024. The point of interconnection is the 99 BENHUR 69kV substation. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Limestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lavender Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
99 BENHUR 69kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.