Leighton Solar SLF (ERCOT-24INR0298) — Project Summary

Queue ID
ERCOT-24INR0298
Capacity
183 MW
Technology
Solar
Status
active
Location
Limestone, TX
Region
ERCOT
Developer
Lavender Solar LLC
IA Status
IA Executed

Leighton Solar SLF

ERCOT-24INR0298BetaActiveSolarERCOTLBNL + Live

183 MW generation in Limestone, TX · In queue since May 2022 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

183 MW

Capacity

1

Components

Solar

4y 6m

In Queue

IA Executed

IA Phase

Signed May 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2 years

IA → COD

3y 7m

Total Duration

2 years

Construction75%
Queue EntryMay 11, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 28, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-12-06

Queue history
24INR0298 · 54 monthly ERCOT reports, Apr 2022 – Sep 2026

Projected COD moved

7 times

Nov 2024 → Dec 2027

Net change

+37 months

first report to latest

Capacity

180 → 181 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 11, 2022
Interconnection agreement signedMay 28, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Sep 1, 2027
Differs from queue: Dec 6, 2027From queue filing
Developer in saved assessment
RKB Energy
Filed as Lavender Solar LLC
Status at research time
IA Executed
IA Executed — interconnection agreement signed May 2024, FIS (Facility Interconnection Study) pending per ercotqueue.com tracker
Financing
Not recorded

Milestones in this assessment

IA executedMay 28, 2024

Interconnection Agreement executed with ERCOT

interconnection.fyi
COD targetSep 1, 2027Latest in this assessment

Proposed commercial operation date per latest ERCOT capacity charts

ercot.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. interconnection.fyi/project/ercot-24inr0298
  2. cleanview.co/power-projects/developers/rkb-energy
  3. ercotqueue.com/developer/lavender-solar-llc
  4. ercot.com/files/docs/2026/02/05/Capacity-Changes-by-Fuel-Type-Charts_January_2026.xlsx
  5. ercot.com/files/docs/2024/12/06/Capacity%20Changes%20by%20Fuel%20Type%20Charts_November_2024.xlsx

Commercial operation date: LBNL queue shows September 2027 COD. ERCOT capacity charts from late 2024 showed 2026 target, but more recent ERCOT charts (Nov 2025, Jan 2026) confirm 2027, indicating a ~1-year slip that has now stabilized in official filings.

Developer: LBNL filing uses 'Lavender Solar LLC' (project SPV). Cleanview's RKB Energy pipeline page lists Leighton Solar SLF as one of RKB's top projects, identifying RKB Energy as the operating developer behind the Lavender Solar shell entity.

Status: LBNL shows IA executed 2024-05-28. ERCOT queue tracker confirms project is at IA stage with FIS pending, consistent with active pre-construction phase.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Leighton Solar SLF project is a proposed 183 MW solar generation project located in Limestone County, Texas. Developed by Lavender Solar LLC, the project is in the ERCOT interconnection queue as entry ERCOT-24INR0298, with a queue entry date of May 11, 2022. The proposed commercial operation date is September 1, 2027.

The project's interconnection agreement has been executed as of May 28, 2024. The point of interconnection is the 99 BENHUR 69kV substation. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Limestone

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Lavender Solar LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

99 BENHUR 69kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.