Rubicon Alpha Wind
225.6 MW generation in Haskell, TX · In queue since May 2022 · Proposed COD July 2027
225.6 MW
Capacity
1
Components
Wind
4y 6m
In Queue
IA Executed
IA Phase
Signed May 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2 years
IA → COD
3y 2m
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–36 months
Proposed COD: 2027-07-31
Projected COD moved
2 times
Aug 2024 → Jul 2027
Net change
+35 months
first report to latest
Capacity
228 → 223 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
ERCOT Standard Generation Interconnection Agreement executed between Electric Transmission Texas, LLC and Throckmorton Wind, LLC
interchange.puc.texas.govTarget commercial operation date per ERCOT capacity planning documents
ercot.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=1816
- ercot.com/files/docs/2026/02/05/Capacity-Changes-by-Fuel-Type-Charts_January_2026.xlsx
- ercotqueue.com/project/24INR0291
- assets.comptroller.texas.gov/ch313/1905/1905-haskell-stetson-cert.pdf
- ercot.com/files/docs/2025/02/12/CapacityDemandandReservesReport_December2024.pdf
Commercial operation date: LBNL proposed COD of July 2027 is consistent across all ERCOT capacity charts (May 2024, September 2025, January 2026). No press releases or news articles found to contradict or update this target.
Developer: All sources consistently identify Throckmorton Wind, LLC as the developer. No parent company or operating entity identified in search results. The entity appears to be the actual developer rather than a shell LLC, as it's associated with multiple projects (Rubicon Alpha, Rubicon Echo, Throckmorton Wind per Texas Comptroller document).
Status: LBNL shows 'active' status with IA executed May 8, 2024. Texas PUC filings confirm interconnection agreement with Electric Transmission Texas. Third-party queue analytics (ercotqueue.com) assess 95% build chance based on IA + FIS completion.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Rubicon Alpha Wind is a proposed 225.6 MW wind generation project located in Haskell County, Texas. The developer is Throckmorton Wind, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0291, with a queue entry date of May 10, 2022, and a proposed commercial operation date of July 31, 2027.
The project's interconnection agreement has been executed as of May 8, 2024. Recent news coverage has discussed the development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Haskell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Throckmorton Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60507 pendulo7A 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Max 4 Wind
Data tables and metrics from the InfraSure database.
FPL Energy Oliver Wind II LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Wind queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Rubicon Alpha Wind
Data-driven briefing on Rubicon Alpha Wind — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.