Rubicon Alpha Wind (ERCOT-24INR0291) — Project Summary

Queue ID
ERCOT-24INR0291
Capacity
225.6 MW
Technology
Wind
Status
active
Location
Haskell, TX
Region
ERCOT
Developer
Throckmorton Wind, LLC
IA Status
IA Executed

Rubicon Alpha Wind

ERCOT-24INR0291BetaActiveWindERCOTLBNL + Live

225.6 MW generation in Haskell, TX · In queue since May 2022 · Proposed COD July 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

225.6 MW

Capacity

1

Components

Wind

4y 6m

In Queue

IA Executed

IA Phase

Signed May 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2 years

IA → COD

3y 2m

Total Duration

2 years

Construction75%
Queue EntryMay 10, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 8, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2027-07-31

Queue history
24INR0291 · 54 monthly ERCOT reports, Apr 2022 – Sep 2026

Projected COD moved

2 times

Aug 2024 → Jul 2027

Net change

+35 months

first report to latest

Capacity

228 → 223 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 10, 2022
Facilities study approvedMar 13, 2026
Interconnection agreement signedMay 8, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Jul 31, 2027
From queue filing
Developer in saved assessment
Throckmorton Wind, LLC
From queue filing
Status at research time
Active
Active — IA executed May 2024, FIS complete, 95% build probability per queue analytics
Financing
Not recorded

Milestones in this assessment

IA executedMay 8, 2024

ERCOT Standard Generation Interconnection Agreement executed between Electric Transmission Texas, LLC and Throckmorton Wind, LLC

interchange.puc.texas.gov
COD targetJul 31, 2027Latest in this assessment

Target commercial operation date per ERCOT capacity planning documents

ercot.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=1816
  2. ercot.com/files/docs/2026/02/05/Capacity-Changes-by-Fuel-Type-Charts_January_2026.xlsx
  3. ercotqueue.com/project/24INR0291
  4. assets.comptroller.texas.gov/ch313/1905/1905-haskell-stetson-cert.pdf
  5. ercot.com/files/docs/2025/02/12/CapacityDemandandReservesReport_December2024.pdf

Commercial operation date: LBNL proposed COD of July 2027 is consistent across all ERCOT capacity charts (May 2024, September 2025, January 2026). No press releases or news articles found to contradict or update this target.

Developer: All sources consistently identify Throckmorton Wind, LLC as the developer. No parent company or operating entity identified in search results. The entity appears to be the actual developer rather than a shell LLC, as it's associated with multiple projects (Rubicon Alpha, Rubicon Echo, Throckmorton Wind per Texas Comptroller document).

Status: LBNL shows 'active' status with IA executed May 8, 2024. Texas PUC filings confirm interconnection agreement with Electric Transmission Texas. Third-party queue analytics (ercotqueue.com) assess 95% build chance based on IA + FIS completion.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Rubicon Alpha Wind is a proposed 225.6 MW wind generation project located in Haskell County, Texas. The developer is Throckmorton Wind, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0291, with a queue entry date of May 10, 2022, and a proposed commercial operation date of July 31, 2027.

The project's interconnection agreement has been executed as of May 8, 2024. Recent news coverage has discussed the development.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Haskell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Throckmorton Wind, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

60507 pendulo7A 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.