Royal River BESS
310.7 MW storage in Brazoria, TX · In queue since March 2022 · Proposed COD June 2028
310.7 MW
Capacity
1
Components
Battery
4y 8m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
Projected COD moved
4 times
Dec 2024 → Jun 2028
Net change
+42 months
first report to latest
Capacity
307 → 311 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
ERCOT Generator Interconnection Status data lists an interconnection agreement date of 2023-12-15, though LBNL shows no IA date.
app.nrgmap.comResearch sources and reasoning (5 recorded sources)
low confidence at research time
- app.nrgmap.com/queues/ercot-24inr0282
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0282/royal-river-bess
- infrasure.ai/project/ercot-24inr0282-royal-river-bess
- ercotqueue.com/project/24INR0282
- interconnection.fyi/project/ercot-24inr0282
Commercial operation date: NRG Map (ERCOT status data as of 2026-09-01) and Cleanview both show a proposed online date of June 2028, which matches LBNL's 2028-06-30. These aggregators repeat the same queue data, so there is no independent developer-backed COD. Infrasure's 2027 figure contradicts itself (June 2027 vs. January 2027) and appears to be a derived estimate, so I did not use it.
Developer: Every source, including the LBNL filing, ERCOT-derived trackers and Infrasure, names only Royal River LLC. No press release or news item identifies a parent or operating company, so the project-LLC name is the only known developer.
Status: NRG Map reports 'Status active as of 1 September 2026', which is consistent with LBNL. Trackers disagree on IA progress, and Texas PUC filings from March and April 2026 reference the project, which fits continued interconnection activity. Nothing indicates construction, withdrawal or suspension.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Royal River BESS is a proposed 310.7 MW battery storage project in Brazoria County, Texas. Developed by Royal River LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-24INR0282. It entered the interconnection queue on March 30, 2022, and has a proposed commercial operation date of January 11, 2027. The project's interconnection status is currently in the Facility Study phase.
The Royal River BESS development has been the subject of recent news coverage, with four articles focusing on deals related to the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Royal River LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 42110 Angleton - 43381 West Columbia
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BCH_RN
- POI Substation
- Angleton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.