Wensowitch Solar
146.08 MW generation in Navarro, TX · In queue since January 2022 · Proposed COD April 2029
146.08 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-17
Projected COD moved
10 times
Oct 2024 → Apr 2029
Net change
+54 months
first report to latest
Capacity
146 → 146 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Proposed COD updated from September 2027 to March 2028
interconnectionfyi.substack.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- gem.wiki/Wensowitch_Solar_Park_solar_farm
- renewablesinfo.org/plant/67567-wensowitch-solar-park
- eia.gov/electricity/monthly/xls/table_6_05.xlsx
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-db7
- live.euronext.com/sites/default/files/company_press_releases/attachments_oslo/2026/04/30/672148_Greenalia%20S.A.%20and%20Subsidiaries%20-%20FY25%20Audited%20Consolidated%20Financial%20Statements.pdf
Commercial operation date: LBNL proposes September 2028 COD. Interconnection.fyi newsletter (May 2025) notes a COD shift from Sept 2027 to March 2028, confirming the project remains in 2028 timeframe. No financing announcements or construction milestones found to refine further.
Developer: LBNL filing uses project-specific LLC 'Greenalia Solar Power Wensowitch LLC'. Multiple sources (GEM.wiki, renewablesinfo.org, EIA) identify parent as 'Greenalia'. Euronext filing confirms Greenalia S.A. owns the 189 MWdc Wensowitch project as part of its portfolio.
Status: LBNL status is 'active' at Facility Study stage. Interconnection.fyi May 2025 update confirms project remains active with updated COD target. No withdrawal or construction signals found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Wensowitch Solar project is a proposed 146.08 MW solar generation facility in Navarro County, Texas. The project, developed by Greenalia Solar Power Wensowitch LLC, is in the ERCOT interconnection queue as entry ERCOT-24INR0205, with a queue entry date of January 7, 2022, and a proposed commercial operation date of September 8, 2028. Its interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Wensowitch Solar Park operating plant (EIA ID 67567). Recent news coverage has discussed the development project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greenalia Solar Power Wensowitch LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tapping 138 kV line Telico (192) to Montfort Switch (3454)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- TRSES_UNIT6
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Wensowitch Solar
Data-driven briefing on Wensowitch Solar — fleet, generation, financial, and news signals.
Greenalia Solar Power Blackwelder Ranch
Data-driven briefing on Greenalia Solar Power — fleet, generation, financial, and news signals.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.