Cumulus Grid BESS
210.74 MW storage in Ellis, TX · In queue since March 2022 · Proposed COD January 2028
210.74 MW
Capacity
1
Components
Battery
4y 8m
In Queue
IA Executed
IA Phase
Signed Jun 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 3m
IA → COD
2y 7m
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2028-01-01
Projected COD moved
5 times
May 2025 → Jan 2028
Net change
+32 months
first report to latest
Capacity
206 → 211 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Standard Generation Interconnection Agreement executed with Oncor
interchange.puc.texas.govProposed completion date updated from May 31, 2027 to December 31, 2027
interconnectionfyi.substack.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-7d3
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0178/cumulus-grid-bess
- interconnection.fyi/project/ercot-24inr0178
Commercial operation date: LBNL shows 2028-01-01, but Interconnection.fyi weekly update from Jan 6, 2025 reports the proposed completion changed from May 31, 2027 to December 31, 2027, reflecting a more recent filing update.
Developer: LBNL filing entity 'Cumulus Grid, LLC' appears to be the operating company itself rather than a shell LLC. No evidence of parent company or ownership transfer found in search results.
Status: LBNL shows 'active' with IA executed on 2025-06-03. Texas PUC filing from July 2025 confirms Amendment No. 2 to Standard Generation Interconnection Agreement, indicating active progression through interconnection process.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Cumulus Grid BESS project is a proposed 210.74 MW battery storage project located in Ellis County, Texas. Developed by Cumulus Grid, LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0178, with a queue entry date of March 14, 2022.
The proposed commercial operation date for the Cumulus Grid BESS project is January 1, 2028. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the 1906 Venus Switch Substation 345kV. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Ellis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cumulus Grid, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1906 Venus Switch Substation 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-07-10
View all articlesCumulus Grid BESS
Data-driven briefing on Cumulus Grid BESS — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.