Briefing/projectactive
Cumulus Grid BESS is a 211 MW Battery project in Texas, currently active.
Cumulus Grid, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-01-01.
- Queue ID
- ERCOT-24INR0178
- Location
- Ellis, Texas
- Technology
- Battery
- Developer
- Cumulus Grid, LLC
- Market / region
- ERCOT
- Point of interconnection
- 1906 Venus Switch Substation 345kV
What stands out
1
Cumulus Grid BESS is a 211 MW Battery project in Texas with status active.
2
Cumulus Grid, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2028-01-01.
4
Latest linked story: “Texas gaining 600 MWh battery project with Navboot Holdco, LLC” (BIC Magazine, 2026-01-07).
Market and operating context
- Queue date
- 2022-03-14
- Proposed COD
- 2028-01-01
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.