Solar Star North Herty Storage
125.9 MW storage in Angelina, TX · In queue since February 2022 · Proposed COD August 2027
125.9 MW
Capacity
1
Components
Battery
4y 9m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-25
Projected COD moved
2 times
Jun 2024 → Aug 2027
Net change
+38 months
first report to latest
Capacity
125 → 126 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Angelina County Commissioners approved revised economic development agreement for Solar Star North Herty Storage facility
ktre.comProposed completion date updated from April 2026 to August 2027
interconnectionfyi.substack.comResearch sources and reasoning (4 recorded sources)
low confidence at research time
- ktre.com/2024/09/24/angelina-county-commissioners-approve-support-over-800m-energy-projects/
- lufkindailynews.com/news/local/county-oks-revised-agreement-for-80-million-energy-storage-facility/article_24c3bd5a-99da-5f08-92bc-d40977d7e69b.html
- angelinacounty.net/files/pdf/agendas/COM-AGEN092424.pdf
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-442
Commercial operation date: LBNL proposes COD of August 25, 2027. One Interconnection Weekly mention (Feb 2025) notes the proposed completion changed from April 2026 to August 2027, confirming the LBNL date is current. No developer press releases or financing announcements provide alternative targets.
Developer: LBNL filing entity is 'Solar Star North Herty Storage, LLC' — a project-specific LLC. No news sources identify the parent operating company or developer. County records and subsidy trackers only reference the LLC itself.
Status: LBNL status is 'active' at Facility Study stage. Angelina County Commissioners approved a revised economic development agreement in September 2024, indicating active local permitting and project advancement.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Solar Star North Herty Storage is a proposed 125.4 MW battery storage project in Angelina County, Texas. The project is being developed by Solar Star North Herty Storage, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0174, with a queue entry date of February 21, 2022, and a proposed commercial operation date of August 25, 2027. Its interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 125.4 MW of battery storage capacity. The point of interconnection is at the 3319 Redland Switch 138 kV location. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Angelina
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Solar Star North Herty Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3307 Redland Switch 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.