Briefing on Solar Star North Herty Storage

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
126 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-08-25
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Solar Star North Herty Storage is a 126 MW Battery project in Texas, currently active.

Solar Star North Herty Storage, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-08-25.

Queue ID
ERCOT-24INR0174
Location
Angelina, Texas
Technology
Battery
Developer
Solar Star North Herty Storage, LLC
Market / region
ERCOT
Point of interconnection
3307 Redland Switch 138 kV

What stands out

1

Solar Star North Herty Storage is a 126 MW Battery project in Texas with status active.

2

Solar Star North Herty Storage, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-08-25.

Market and operating context

Queue date
2022-02-21
Proposed COD
2027-08-25
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Solar Star North Herty Storage — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0174
LocationAngelina, Texas
TechnologyBattery
DeveloperSolar Star North Herty Storage, LLC
Market / regionERCOT
Point of interconnection3307 Redland Switch 138 kV
Queue date2022-02-21