Merope BESS
402.44 MW storage in Comanche, TX · In queue since December 2021 · Proposed COD March 2028
402.44 MW
Capacity
1
Components
Battery
4y 11m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
Projected COD moved
3 times
Mar 2024 → Mar 2028
Net change
+48 months
first report to latest
Capacity
414 → 402 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
- —·Broad Reach Power (BRP Merope BESS LLC)→Engiecleanview.co
Research sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0157/merope-bess
- cleanview.co/power-projects/developers/engie
- infrasure.ai/project/ercot-24inr0157-merope-bess
- interconnection.fyi/project/ercot-24inr0157
Commercial operation date: Every source that gives a date (Cleanview 'expected to come online in March 2028', Infrasure, interconnection.fyi) repeats the LBNL/ERCOT proposed COD of 2028-03-01. No developer press release or financing-backed target was found, so there is no independent post-LBNL signal.
Developer: The LBNL filing entity 'BRP Merope BESS LLC' appears to be a Broad Reach Power project shell. Cleanview's Engie developer page lists Merope BESS (402 MW, Texas) in Engie's pipeline, which suggests Engie now owns it after acquiring Broad Reach Power. The BRP-to-Broad Reach Power link and the acquisition itself are my inference and are not confirmed in the snippets, so this is low confidence.
Status: LBNL shows 'active' and the queue aggregators (interconnection.fyi, Infrasure) agree. Nothing indicates withdrawal, suspension or construction start.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Merope BESS project is a proposed 401.92 MW battery storage project located in Comanche County, Texas. The developer is BRP Merope BESS LLC. It is interconnected within the ERCOT region, queue ID ERCOT-24INR0157, having entered the queue on December 20, 2021. The proposed commercial operation date is March 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists solely of battery storage, with a total capacity of 401.92 MW. Recent news coverage indicates public interest in the development. The point of interconnection is the 345 kV Corn Trail Switch Substation (#11441).
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Comanche
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Merope BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Corn Trail Switch Substation (#11441)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Substation 41
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.