Moonstone Solar Project (ERCOT-24INR0156) — Project Summary

Queue ID
ERCOT-24INR0156
Capacity
145.81 MW
Technology
Solar
Status
active
Location
Wilson, TX
Region
ERCOT
Developer
Moon Stone Solar Farm, LLC
IA Status
IA Executed

Moonstone Solar Project

ERCOT-24INR0156BetaActiveSolarERCOTLBNL + Live

145.81 MW generation in Wilson, TX · In queue since October 2021 · Proposed COD March 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

145.81 MW

Capacity

1

Components

Solar

5y 1m

In Queue

IA Executed

IA Phase

Signed Feb 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 4m

IA → COD

4y 1m

Total Duration

3y 4m

Construction75%
Queue EntryOct 27, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 17, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2029-03-31

Queue history
24INR0156 · 52 monthly ERCOT reports, Jun 2022 – Sep 2026

Projected COD moved

4 times

May 2024 → Mar 2029

Net change

+58 months

first report to latest

Capacity

146 → 175 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedOct 27, 2021
Facilities study approvedJan 18, 2024
Interconnection agreement signedFeb 17, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2029
Developer in saved assessment
Scout Clean Energy
Filed as Moon Stone Solar Farm, LLC
Status at research time
Active
Active — IA executed Feb 2025, preliminary interconnection work with CPS Energy underway, switchyard construction planned for 2027, project construction targeted for 2028
Financing
Not recorded

Milestones in this assessment

IA executedFeb 17, 2025

Interconnection Agreement executed with ERCOT

wilsoncountynews.com
Permit approvedMar 2026

Scout Clean Energy presented project to Wilson County Commissioners Court, 2,600 acres signed with private landowners

wilsoncountynews.com
Groundbreaking2027

Switchyard construction to connect to CPS Energy transmission line planned to start

wilsoncountynews.com
Groundbreaking2028

Main project construction estimated to begin

wilsoncountynews.com
COD target2029Latest in this assessment

Commercial operation date target when project will be plugged into grid

wilsoncountynews.com
Research sources and reasoning (3 recorded sources)

high confidence at research time

  1. wilsoncountynews.com/articles/moonstone-solar-project-aims-for-floresville-area/
  2. now.solar/2026/03/25/moonstone-solar-project-aims-for-floresville-area-wilson-county-news/
  3. ercotqueue.com/developer/moon-stone-solar-farm-llc

Commercial operation date: LBNL proposed COD of 2029-03-31 aligns with Scout Clean Energy's public presentation to Wilson County commissioners on March 23, 2026, where they stated 'targeting 2029 as a commercial operation date' with construction estimated to begin in 2028.

Developer: Wilson County News article from March 2026 identifies 'Scout Clean Energy, based in Boulder, Colo.' as the project developer presenting to commissioners, while LBNL filing uses project-LLC 'Moon Stone Solar Farm, LLC'. One aggregator site (renewablesinfo.org) also lists 'Ignis TX Solar One LLC' as developer, suggesting possible shell-entity complexity.

Status: LBNL status 'active' with IA executed 2025-02-17 is confirmed by Scout Clean Energy's March 2026 public presentation detailing active development timeline and signed land agreements for 2,600 acres.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Moonstone Solar Project is a proposed 145.81 MW solar generation project located in Wilson County, Texas. The developer is Ignis TX Solar One LLC. It is listed in the ERCOT interconnection queue as entry ERCOT-24INR0156, with a queue entry date of October 27, 2021, and a proposed commercial operation date of March 31, 2029.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV Eagle Creek (5132) to Floresville (5155). The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Wilson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Moon Stone Solar Farm, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV Eagle Creek (5132) to Floresville (5155)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.