De Los Santos (ERCOT-24INR0142) — Project Summary

Queue ID
ERCOT-24INR0142
Capacity
200.97 MW
Technology
Battery
Status
active
Location
Maverick, TX
Region
ERCOT
Developer
BRP De Los Santos BESS LLC
IA Status
Facility Study

De Los Santos

ERCOT-24INR0142BetaActiveBatteryERCOTLBNL + Live

200.97 MW storage in Maverick, TX · In queue since May 2022 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

200.97 MW

Capacity

1

Components

Battery

4y 6m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 7m

Facilities Study50%
Queue EntryMay 10, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Queue history
24INR0142 · 54 monthly ERCOT reports, Apr 2022 – Sep 2026

Projected COD moved

2 times

Mar 2024 → Dec 2027

Net change

+45 months

first report to latest

Capacity

207 → 201 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 10, 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Dec 1, 2027
From queue filing
Developer in saved assessment
BRP De Los Santos BESS LLC
From queue filing
Status at research time
Active
Active — Facility Study stage, no public construction timeline or financing announcements
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0142/de-los-santos
  2. interconnection.fyi/project/ercot-24inr0142
  3. modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
  4. ercotqueue.com/project/24INR0142
  5. ercotqueue.com/developer/brp-de-los-santos-bess-llc

Commercial operation date: Only LBNL queue data provides a COD target of December 2027. No press releases, financing announcements, or developer updates found to validate or contradict this date.

Developer: LBNL filing entity 'BRP De Los Santos BESS LLC' appears to be a project-specific LLC, but no parent company or operating entity could be identified from available sources. No press releases or corporate announcements found.

Status: LBNL status shows 'active' in Facility Study phase. No news coverage or developer updates found to indicate progression beyond interconnection studies.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The De Los Santos project is a proposed 200.97 MW battery storage project located in Maverick County, Texas. The developer is BRP De Los Santos BESS LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0142, with a queue entry date of May 10, 2022.

The proposed commercial operation date for the De Los Santos project is December 1, 2027. Its interconnection point is the 78016 Sunglow Substation 138kV. The project's interconnection status is currently in the Facility Study phase.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Maverick

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BRP De Los Santos BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

78016 Sunglow Substation 138kV

Data Source

LBNL + Live

CompanyUS Department of EnergyTexas Standard · 2018-04-24
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-09

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.