Midpoint Storage
50.9 MW storage in Hill, TX · In queue since October 2021 · Proposed COD March 2026
50.9 MW
Capacity
1
Components
Battery
4y 9m
In Queue
IA Executed
IA Phase
Signed Oct 2023
Queue → IA
2 years
IA → COD
2y 5m
Total Duration
2 years
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-03-13
Midpoint Storage is a proposed 50.9 MW battery storage project located in Hill County, Texas. The project, developed by Midpoint Solar, LLC, is interconnected within the Electric Reliability Council of Texas (ERCOT) queue under queue ID ERCOT-24INR0138. The project entered the queue on October 15, 2021, and has a proposed commercial operation date of March 13, 2026. The interconnection agreement (IA) for the project was executed on October 31, 2023.
The proposed project consists of 50.9 MW of battery storage capacity. Midpoint Storage has been featured in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hill
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Midpoint Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 KV Tap #3518 BLUM to #237 Blanton
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Midpoint StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.