Midpoint Storage
50.9 MW storage in Hill, TX · In queue since October 2021 · Proposed COD February 2026
50.9 MW
Capacity
1
Components
Battery
5y 1m
In Queue
IA Executed
IA Phase
Signed Oct 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2 years
IA → COD
2y 4m
Total Duration
2 years
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-02-19
Projected COD moved
5 times
Dec 2024 → Mar 2026
Net change
+15 months
first report to latest
Capacity
52 → 51 MW
changed in the reports
Latest stage
Commercial operation
last listed Jun 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
About
Generated Apr 10, 2026 · Predates Jun 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Midpoint Storage is a proposed 50.9 MW battery storage project located in Hill County, Texas. The project, developed by Midpoint Solar, LLC, is interconnected within the Electric Reliability Council of Texas (ERCOT) queue under queue ID ERCOT-24INR0138. The project entered the queue on October 15, 2021, and has a proposed commercial operation date of March 13, 2026. The interconnection agreement (IA) for the project was executed on October 31, 2023.
The proposed project consists of 50.9 MW of battery storage capacity. Midpoint Storage has been featured in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jun 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hill
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Midpoint Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 KV Tap #3518 BLUM to #237 Blanton
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MIDP_SLR_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Midpoint Storage
Data-driven briefing on Midpoint Storage — fleet, generation, financial, and news signals.
Midpoint Solar, LLC
Data-driven briefing on Midpoint Solar, LLC — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.