Briefing on Midpoint Storage

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
51 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2026-03-13
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Midpoint Storage is a 51 MW Battery project in Texas, currently active.

Midpoint Solar, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-03-13.

Queue ID
ERCOT-24INR0138
Location
Hill, Texas
Technology
Battery
Developer
Midpoint Solar, LLC
Market / region
ERCOT
Point of interconnection
138 KV Tap #3518 BLUM to #237 Blanton

What stands out

1

Midpoint Storage is a 51 MW Battery project in Texas with status active.

2

Midpoint Solar, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-03-13.

Market and operating context

Queue date
2021-10-15
Proposed COD
2026-03-13
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Midpoint Storage — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0138
LocationHill, Texas
TechnologyBattery
DeveloperMidpoint Solar, LLC
Market / regionERCOT
Point of interconnection138 KV Tap #3518 BLUM to #237 Blanton
Queue date2021-10-15
Proposed COD2026-03-13