BRP Triton BESS
205.36 MW storage in Comanche, TX · In queue since October 2021 · Proposed COD December 2026
205.36 MW
Capacity
1
Components
Battery
5y 1m
In Queue
Facility Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
Projected COD moved
3 times
Dec 2023 → Dec 2026
Net change
+36 months
first report to latest
Capacity
205 MW
unchanged in the reports
Latest stage
Cancelled
last listed Jan 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- renewablesinfo.org/project/ercot-24inr0111-brp-triton-bess
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
- interconnection.fyi/projects/state/TX
- ercotqueue.com/developer/brp-triton-bess-llc
Commercial operation date: LBNL queue snapshot shows proposed COD of 2026-12-01. No independent news sources or press releases found to confirm or contradict this date; search results only echo queue data.
Developer: Only source is LBNL filing entity 'BRP Triton BESS LLC'. No press releases, corporate announcements, or news coverage found identifying a parent company or operating entity. Entity appears to be a project-specific LLC with no public parent disclosed.
Status: LBNL status is 'active' with IA status at 'Facility Study'. One search result (interconnection.fyi) lists status as 'Withdrawn', but this conflicts with LBNL authoritative data and may be outdated or erroneous. No corroborating evidence of withdrawal found.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The BRP Triton BESS project is a proposed 205.36 MW battery storage project located in Comanche County, Texas. Developed by BRP Triton BESS LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0111, with a queue entry date of October 18, 2021.
The proposed commercial operation date for the BRP Triton BESS project is December 1, 2026. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the 138 kV Comanche Switch Substation (#1441). The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jan 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Comanche
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Triton BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Comanche Switch Substation (#1441)
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Comanche
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
BRP Triton BESS
Data-driven briefing on BRP Triton BESS — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.