Louisa Energy Storage
102.77 MW storage in Bexar, TX · In queue since November 2021 · Proposed COD March 2029
102.77 MW
Capacity
1
Components
Battery
5 years
In Queue
IA Executed
IA Phase
Signed Feb 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 3m
IA → COD
4y 1m
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2029-03-12
Projected COD moved
3 times
Aug 2023 → Mar 2029
Net change
+67 months
first report to latest
Capacity
103 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed between VESI 49 LLC and CPS Energy for Louisa Energy Storage
interchange.puc.texas.govResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- ercot.com/files/docs/2025/03/07/CapacityChangesbyFuelTypeCharts_February_2025.xlsx
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
- interchange.puc.texas.gov/Documents/35077_2075_1473686.PDF
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-602
Commercial operation date: LBNL queue shows proposed COD of 2029-03-12. ERCOT capacity chart (Feb 2025) lists 2026 as target year, but this appears to be a data entry error given the recent IA execution date of Feb 2025. No press releases or developer announcements found to confirm actual target.
Developer: LBNL filing entity is 'VESI 49 LLC' (project shell). ERCOT buildout pipeline (May 2024) identifies parent as 'Viridity Energy Solutions Inc.' VESI likely stands for Viridity Energy Solutions Inc., with numbered LLCs for individual projects.
Status: LBNL shows 'IA Executed' status with IA date of 2025-02-27. Texas PUC filing confirms Generation Interconnection Agreement between VESI 49 LLC and CPS Energy filed March 11, 2025. ERCOT buildout report shows FIS completed.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Louisa Energy Storage is a proposed 102.77 MW battery storage project located in Bexar County, Texas. The project, developed by VESI 49 LLC, is in the ERCOT interconnection queue as entry ERCOT-24INR0108, with a queue entry date of November 16, 2021. The proposed commercial operation date is March 12, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.
The development has been the subject of recent news coverage, with three articles focusing on deals related to the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bexar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
VESI 49 LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Helotes (#5200)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.