Dovetail Solar 2 (ERCOT-24INR0095) — Project Summary

Queue ID
ERCOT-24INR0095
Capacity
666.1 MW
Technology
Solar+Battery
Status
active
Location
Jack, TX
Region
ERCOT
Developer
Hecate Energy Dovetail Solar 2 LLC
IA Status
Facility Study

Dovetail Solar 2

ERCOT-24INR0095BetaActiveSolarBatteryERCOTLBNL + Live

666.1 MW hybrid in Jack, TX · In queue since October 2021 · Proposed COD April 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

666.1 MW

Capacity

1

Components

Solar

5y 1m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

7y 6m

Facilities Study50%
Queue EntryOct 26, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-04-20

Queue history
24INR0095 · 51 monthly ERCOT reports, Jul 2022 – Sep 2026

Projected COD moved

3 times

Nov 2025 → Apr 2029

Net change

+41 months

first report to latest

Capacity

666 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedOct 26, 2021

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 20, 2029
From queue filing
Developer in saved assessment
Hecate Energy
Filed as Hecate Energy Dovetail Solar 2 LLC
Status at research time
Active
Active in ERCOT queue at Facility Study stage; no IA executed and no public construction or financing news found.
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/ercot-24inr0095
  2. cleanview.co/power-projects/planned/solar-farms/texas/24INR0095/dovetail-solar-2
  3. infrasure.ai/project/ercot-24inr0095-dovetail-solar-2
  4. opencorporates.com/companies/us_tx/0804581432
  5. texas-biz.com/co/hecate-energy-dovetail-solar-2-llc

Commercial operation date: Only the LBNL/ERCOT queue date (2029-04-20) exists. Aggregators (interconnection.fyi, cleanview.co) repeat it as 'expected online 2029', but they derive it from the queue and add no independent post-LBNL signal.

Developer: The LBNL filing entity is a project LLC whose name embeds the Hecate Energy brand; corporate registries list it at 621 W Randolph St, Chicago. No press release or news confirms the current parent or any ownership change, so the parent is inferred from the entity name.

Status: LBNL and queue aggregators (interconnection.fyi, Grid Status) show the project as active, with IA status 'Facility Study' and no IA date. No contradicting signal appears.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Dovetail Solar 2 is a proposed solar generation project located in Jack County, Texas, with a total capacity of 666.1 MW. The project is being developed by Hecate Energy Dovetail Solar 2 LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0095, with a queue entry date of October 26, 2021, and a proposed commercial operation date of April 20, 2029. The project's interconnection agreement status is currently in the Facility Study phase.

The point of interconnection for Dovetail Solar 2 is Tap 345 KV 1421 Willow Creek - 60515 Clear Crossing. The project has appeared in recent news coverage regarding solar development in Texas.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Jack

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Hecate Energy Dovetail Solar 2 LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345 KV 1421 Willow Creek - 60515 Clear Crossing

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
WCPP_CC1
POI Substation
Willow Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.